An Analysis of Voltage Quality in a Nanogrid during Islanded Operation

Størrelse: px
Starte visningen fra side:

Download "An Analysis of Voltage Quality in a Nanogrid during Islanded Operation"

Transkript

1 energies Article An Analysis of Voltage Quality in a Nanogrid during Islanded Operation Jakob Nömm *, Sarah K. Rönnberg * and Math H. J. Bollen * Electric Power Engineering, Luleå University of Technology, Skellefteå, Sweden * Correspondence: jakob.nomm@ltu.se (J.N.); sarah.ronnberg@ltu.se (S.K.R.); math.bollen@ltu.se (M.H.J.B.) Received: 21 January 2019; Accepted: 13 February 2019; Published: 15 February 2019 Abstract: Voltage quality data has been collected in a single house nanogrid during 48 weeks of islanded operation and 54 weeks of grid-connected operation. The voltage quality data contains the voltage total harmonic distortion (THD), odd harmonics 3 to 11 and 15, even harmonics 4 to 8, voltage unbalance, short-term flicker severity (Pst) and long-term flicker severity (Plt) values, and voltage variations at timescales below 10 min. A comparison between islanded and grid-connected operation values was made, were some of the parameters were compared to relevant grid standard limits. It is shown that some parameters exceed the defined limits in the grid-standards during islanded operation. It was also found that the islanded operation has two modes of operation, one in which higher values of the short circuit impedance, individual harmonic impedance, harmonic voltage distortion and voltage unbalance were reached. Keywords: harmonics; islanded operation; nanogrids; power quality; voltage unbalance 1. Introduction Microgrids and nanogrids can provide economical gains in the form of price reductions for consumers and increased revenue for grid owners [1]. They could also provide an improved technical solutions such as energy loss reduction and better reliability than a regular utility connection for certain geographical areas [1,2]. The international council on large electric systems (CIGRE) WG C6.22 defines microgrids as: electricity distribution systems containing loads and distributed energy resources, (such as distributed generators, storage devices, or controllable loads) that can be operated in a controlled, coordinated way either while connected to the main power network or while islanded [3]. The term nanogrid was suggested in [4] for defining a small microgrid, which could be a single residential house. There is a lack of published papers that contain voltage quality measurements that span several months or years for nanogrids in islanded operation. These measurements are needed to establish the differences in performance between islanded operation and grid-connected operation. The measurements would also make it possible to evaluate if problems can appear for connected equipment during islanded operation. In this paper, long term measurements of voltage quality are presented that have been collected in a single house nanogrid during 48 weeks of islanded operation and 54 weeks of grid-connected operation. Some of the measured voltage quality parameters have been compared with the limits defined in standards EN [5] and IEEE [6]. The specified standards do not include voltage quality limits for islanded operation, so the limits in the standards are only used as a reference for islanded operation. The main contribution of this paper is the analysis and presentation of long-term voltage quality measurements collected in a nanogrid during islanded operation. All the used equipment in the Energies 2019, 12, 614; doi: /en

2 Energies 2019, 12, of 24 Energies 2018, 11, x FOR PEER REVIEW 2 of 27 nanogrid nanogrid is is commercially available available and and therefore therefore similar similar performance performance is is expected expected for for other other nanogrids like like the the one one presented presented in in this this paper. paper. The Nanogrid 1.1. The Nanogrid The single house nanogrid that is studied in this paper is located in the southern part of Sweden The single house nanogrid that is studied in this paper is located in the southern part of Sweden and has 22.6 kwp solar installation, 144 kwh lead acid battery storage, 1100 kwh hydrogen and has a 22.6 kwp solar installation, 144 kwh lead acid battery storage, 1100 kwh hydrogen storage storage and a 15 kva diesel backup generator. The nanogrid is designed to operate as a 50 Hz and a 15 kva diesel backup generator. The nanogrid is designed to operate as a 50 Hz three-phase three-phase system where each phase has a phase-to-neutral voltage of 230 V root mean square system where each phase has a phase-to-neutral voltage of 230 V Root Mean Square (RMS). The (RMS). The consumption in the nanogrid consists of ordinary household appliances, two electric cars, consumption in the nanogrid consists of ordinary household appliances, two electric cars, a threephase heat pump and an electrolyzer for the production of hydrogen. A simplified schematic of the a three-phase heat pump and an electrolyzer for the production of hydrogen. A simplified schematic of the nanogrid energy system can be seen in Figure 1. nanogrid energy system can be seen in Figure 1. Figure Figure Simplified schematic of of the the energy system for for the the nanogrid. Reproduced with permission from from [7], [7], Nömm, Nömm, J.; J.; Rönnberg, S.K.; S.K.; Bollen, M.H.J. An Analysisof of Frequency Variationsand andits its Implications on Connected Equipment for a Nanogrid during Islanded Operation. Energies Energies 2018, 2018, 11, 11, The nanogrid is is designed to run primarily on the produced solar power and the stored energy in in the batteries and hydrogen tanks. During the day, the solar panels will supply the energy to the loads where the excess solar power will charge the batteries and power a 5 kw electrolyzer to to convert electricity to hydrogen that is is stored in in high-pressure tanks. During the night, the batteries are the main supply of energy to the nanogrid; if if the battery charge drops below 30%, a 5 kw fuel cell will convert hydrogen to electricity to charge the battery. If If there is is a malfunction in the primary energy system, the nanogrid will connect to to the low-voltage utility grid. The nanogrid also connects to the utility grid if if the stored energy in in the batteries and hydrogen tanks is is depleted. The backup diesel generator in in the nanogrid is is designed to to start only if if both the low voltage utility grid and the primary energy system in in the nanogrid fail to to operate. The backup diesel generator operated for 43 h during the 48 week islanded operation measurement period. The nanogrid switched to grid-connected operation mainly due to lack of energy stored in the batteries and hydrogen tanks. To To avoid this, additional hydrogen storage is under is under construction. For For more more information regarding the the nanogrid see see [7] [7] and and [8]. [8]. 2. Methodology

3 Energies 2019, 12, of Methodology The measurements have been collected by an Elspec G4430 (Elspec, Caesarea, Israel) connected at the load-output of the SMA Multicluster Box (SMA, Niestetal, Germany). The SMA Multicluster Box is used in the nanogrid since there are three independent solar installations, two on the roof, each with a capacity of 10 kw and one on the facade with 2.6 kw power rating. The parameters measured for the comparison to the limits described in EN and IEEE are the voltage Total Harmonic Distortion (THD), Individual odd harmonics 3rd to 11th and 15th, even harmonics 4th to 8th, Pst, Plt, and voltage unbalance. Two parameters that were also measured with no relation to any standard were the very short variations (VSV) of the voltage and RMS value of the neutral current. For the measured parameters, the total time in islanded operation was 48 weeks and 54 weeks in grid-connected operation. The 48 and 54 week measurements are assembled from shorter time windows in which the nanogrid was in islanded or grid-connected operation. For the voltage THD measurements, there was a measurement period of 29 weeks of the total 48 weeks where the nanogrid operated continuously in islanded operation. These measurements were used to see the daily voltage THD variations. For the analysis of the individual harmonics, the odd harmonics 3rd to 11th and 15th and even harmonics 4th to 8th were chosen since they all surpass the limits defined in either standard EN or IEEE sometime during the 48 week islanded operation measurements. Another measurement period of about 8 weeks in islanded operation and about 5 weeks in grid-connected operation was used to study the variations with time in the short circuit impedance measured as the voltage drop against a current rise of larger than 4 A within two cycles. 3. Results 3.1. Total harmonic Distortion The cumulative distribution function (CDF) for the 10 min values of the voltage THD during 48 weeks in islanded operation and 54 weeks in grid-connected operation can be seen in the upper part of Figure 2. In the lower part of Figure 2, the corresponding CDF for the 3 s values is plotted. As expected, the 3 s voltage THD values reach higher values than the 10 min values during both islanded and grid-connected operation. It can also be observed in Figure 2 that the voltage THD is always higher during islanded operation than during grid-connected operation. The maximum values and total average values are also higher for islanded operation which can be seen in Table 1. Table 1. 95% Confidence interval (CI) for the 10 min values, the maximum 10 min value and total average value for all three phases in islanded and grid-connected operation. Operational State 95% CI 10 min Value Max 10 min Value 95% CI 3 s Value Max 3 s Value Total Average Value Islanded 1.34 to 8% 7.83 to 13.01% 1.28 to 8.06% 18.3 to 21.9% 2.23 to 3.82% Grid-connected 0.77 to 1.88% 2.41 to 2.47% 0.76 to 1.88% 2.5% 1.08 to 1.44% In Figure 3, the average voltage THD variations for each hour of the day for 29 weeks can be seen for all three phases. During 29 out of 48 weeks the nanogrid operated in islanded operation that lasted continually throughout the day without connections to the utility grid.

4 3. Results 3.1. Total harmonic Distortion The cumulative distribution function (CDF) for the 10 min values of the voltage THD during 48 Energies 2019, 12, of 24 weeks in islanded operation and 54 weeks in grid-connected operation can be seen in the upper part of Figure 2. Figure 2. Cumulative distribution function (CDF) for the 10 min voltage Total Harmonic Distortion (THD) for the nanogrid during islanded and grid-connected operation (top) and the CDF for the 3 s voltage THD during grid-connected and islanded operation (bottom). Note that the horizontal axis is Energies different 2018, for 11, each x FOR plot. PEER REVIEW 5 of 27 Figure Figure 3. The 3. The 1 h1 h maximum THD value, total average THD THD value value and and upper upper 95% confidence 95% confidence limit for limit for every every hour hour during during the the day day for for 29 weeks of of continuous islanded islanded operation. operation. The black, The black, red and redblue and blue color represents the three phases. Note the difference in vertical scale for each plot. color represents the three phases. Note the difference in vertical scale for each plot. The trend in Figure 3 shows larger THD values during the night than during the day. This indicates that when the solar production starts, the voltage THD level drops due to more parallel sources being activated and increases when there are fewer parallel sources available. One example when the voltage THD suddenly increases during the evening at about the time when the sun sets can be seen in Figure 4. It can be seen that even though the active power remains almost constant the

5 In Figure 5, the odd voltage and current harmonics 3 to 9 are presented for the 1-cycle period ending at about 20 ms and 80 ms in Figure 4. The 3rd voltage harmonic is about the same for phase 1 and 2 and slightly lower for phase 3. After the transition from 8 to 12% voltage THD (seen at around 40 ms in Figure 4), the 5th voltage harmonic increases for two of the three phases and the 7th and 9th voltage harmonic also increase for all three phases. All of the current harmonics increase for phase 1 but the 3rd harmonic for phase 2 decreases by 1.4% and the 3rd and 7th harmonic for phase 3 decrease Energies 2019, 12, of 24 It can be seen that the maximum 1 h values are reached during the night for phase 1 and 3. For phase 2, the maximum occurs in the middle of the day. The total average value and 95% confidence limit for each hour during the day reach the highest values in the morning and night for all 3 phases. Phase 3 has however a smaller variation between night and day in the total average value and 95% confidence limit as phase 1 and 2. A more detailed view of the voltage THD variations during one day can be seen in [9]. The trend in Figure 3 shows larger THD values during the night than during the day. This indicates that when the solar production starts, the voltage THD level drops due to more parallel sources being activated and increases when there are fewer parallel sources available. One example when the voltage THD suddenly increases during the evening at about the time when the sun sets can be seen in Figure 4. It can be seen that even though the active power remains almost constant the voltage THD increases for all three phases which also can be seen in the voltage waveform. The current THD also increases for phase 1 and 3 and decreases for phase 2 which can also be seen in the current waveform. The reactive power changes somewhat for the three phases and the frequency throughout Figure 4 was around 49 Hz. Energies 2018, 11, x FOR PEER REVIEW 6 of 27 Figure Figure4. 4. Example Example of of an an occasionwhen whenthe the voltagethd THD increasesin inthe the evening. The The voltage voltage waveformis is at at the the top top followed by by the the current current waveform, active active power, power, reactive reactive power, power, current current THD THD and and voltage THD. THD. The The black, black, red redand andblue blue color color represents the the three three phases Individual Harmonics

6 Energies 2019, 12, of Individual Harmonics In Figure 5, the odd voltage and current harmonics 3 to 9 are presented for the 1-cycle period ending at about 20 ms and 80 ms in Figure 4. The 3rd voltage harmonic is about the same for phase 1 and 2 and slightly lower for phase 3. After the transition from 8 to 12% voltage THD (seen at around 40 ms in Figure 4), the 5th voltage harmonic increases for two of the three phases and the 7th and 9th voltage harmonic also increase for all three phases. All of the current harmonics increase for phase 1 but the 3rd harmonic for phase 2 decreases by 1.4% and the 3rd and 7th harmonic for phase 3 decrease by 4.35 and 1.34% respectively. Energies 2018, 11, x FOR PEER REVIEW 7 of 27 Figure Individual harmonics of the voltage THD in Figure 4 where the left side is is the the individual harmonics at at the end of of the 1-cycle period at at about ms ms and the the right side at at about ms. ms. The 95% confidence limit for the 10 min values for the odd voltage harmonics 3rd to 11th and 15th and even voltage harmonics 4th to 8th can be seen in the upper part of of Figure The maximum 10 min value can be seen in the lower part of Figure 6. It can be seen that both the maximum 10 min value and the 95% confidence limit value are higher during islanded operation. The odd harmonics differ the most in magnitude from the grid-connected measurements, except the 95% confidence limit value for the 15th harmonic. Phase 1 has higher 95% confidence limits for the odd harmonics until the 11th. In the maximum 10 min values, the even harmonics are several times higher in islanded operation compared to grid-connected operation. The 95% confidence limit for the even harmonics is close to zero for the grid-connected operation. At a shorter time scale of 3 s, which can be seen in Figure 7, the 95% confidence limit is about the same as the 95% 10 min values in Figure 6. But the maximum 3 s value is larger than the 10 min maximum value. The even harmonics have the highest increase from 10 min maximum values to 3 s maximum values. Phase 2 had the lowest 10 min maximum value for most of the harmonic orders, but for the 3 s values it has the highest value for most of the harmonic orders.

7 Figure 5. Individual harmonics of the voltage THD in Figure 4 where the left side is the individual harmonics at the end of the 1-cycle period at about 20 ms and the right side at about 80 ms. Energies 2019, The 12, 95% 614 confidence limit for the 10 min values for the odd voltage harmonics 3rd to 11th and 7 of 24 15th and even voltage harmonics 4th to 8th can be seen in the upper part of Figure 6. Energies 2018, 11, x FOR PEER REVIEW 8 of 27 The maximum 10 min value can be seen in the lower part of Figure 6. It can be seen that both the maximum 10 min value and the 95% confidence limit value are higher during islanded operation. The odd harmonics differ the most in magnitude from the grid-connected measurements, except the 95% confidence limit value for the 15th harmonic. Phase 1 has higher 95% confidence limits for the odd harmonics until the 11th. In the maximum 10 min values, the even harmonics are several times higher in islanded operation compared to grid-connected operation. The 95% confidence limit for the even harmonics is close to zero for the grid-connected operation. At a shorter time scale of 3 s, which can be seen in Figure 7, the 95% confidence limit is about the same as the 95% 10 min values in Figure 6. But the maximum 3 s value is larger than the 10 min maximum value. The even harmonics have the highest increase from 10 min maximum values to 3 s maximum values. Phase 2 had the lowest 10 min maximum value for most of the harmonic orders, but for the 3 s values it has the highest value for most of the harmonic orders. The total average values for both grid-connected and islanded operation can be seen in Table 2. Table 2. Total average value for each measured voltage harmonic for all three phases. Operational 3rd 4th 5th 6th 7th 8th 9th 11th 15th State (%) (%) (%) (%) (%) (%) (%) (%) (%) Figure Figure min 10 95% min confidence 95% 0.01 confidence limit value limit (top) value and (top) the0.61 and maximum the maximum min value 10 min in the value measurements in the measurements 0.95 (bottom) to for the odd 0.83 harmonics rd to to 11th and 15th and even 1.20 harmonics to th to to 8th to (bottom) Islanded for the odd harmonics to 3rd to 11th and 15th and to even harmonics to 1.96 to th to th. The0.18 black, The black, red and blue 0.02 color represents phase 1 to 3 in 1.45 islanded mode Purple color represents all red and blue color represents phase 1 to 3 in islanded mode. Purple color represents all three phases three phases during grid-connected 0.66 operation since the distortion 0.55 differs substantially less between duringgrid- connected to islanded 0.52 operation. grid-connected 0.30 to operation since the distortion differs substantially less 0.34 between to 0.14 the to phases 0.10 to in the phases in comparison to islanded to operation. 10 comparison to Figure Figure s 3 maximum s 95% 95% confidence limit value (top) and andthe the maximum 3 s 3value s value in the in the measurements measurements (bottom) (bottom) for for the the odd harmonics 3rd 3rdto to 11th 11th and and 15th 15th and even and harmonics even harmonics 4th to 8th. 4th to The black, red and blue color represents phase 1 to 3 in islanded mode. Purple color represents all 8th. The black, red and blue color represents phase 1 to 3 in islanded mode. Purple color represents all three phases during grid-connected operation. three phases during grid-connected operation Voltage Unbalance

8 Energies 2019, 12, of 24 The total average values for both grid-connected and islanded operation can be seen in Table 2. Table 2. Total average value for each measured voltage harmonic for all three phases. Energies 2018, 11, x FOR PEER REVIEW 9 of 27 Operational State 3rd (%) 4th (%) 5th (%) 6th (%) 7th (%) 8th (%) 9th (%) 11th (%) 15th (%) The 10 min voltage unbalance for both islanded operation and grid-connected operation can be seen 0.95 to 0.01 to 0.83 to to 0.61 to to 1.20 to 0.63 to 0.20 to Islanded in Figure 8. The voltage unbalance is for the majority of the measured time lower in islanded operation than in grid-connected operation. The maximum 10 min voltage unbalance was 4.6% for 0.30 to 0.66 to Grid-connected to to 0.14 to 0.10 to islanded operation and 1.77 for grid-connected operation. In Figures the 0.17 occurrence 0.15of the maximum voltage unbalance value can be seen. A summary of the 95% CI, maximum 10 min value 3.3. and Voltage total average Unbalance value in islanded and grid-connected operation can be seen in Table 3. The Table 103. min 95% voltage confidence unbalance interval, for the both maximum islanded 10 min operation value and andtotal grid-connected average value operation for all three can be seen in phases Figure in islanded 8. The voltage and grid-connected unbalanceoperation. is for the majority of the measured time lower in islanded operation than in grid-connected operation. The maximum 10 min voltage unbalance was 4.6% for Operational 95% CI 10 min islanded operation and 1.77 for grid-connected operation. Max 10 min In Value Figures Total the Average occurrence Value of the State Value maximum voltage unbalance value can be seen. A summary of the 95% CI, maximum 10 min value Islanded 0.06 to 0.72% 4.6% 0.22% and total average value in islanded and grid-connected operation can be seen in Table 3. Grid-connected 0.11 to 0.68% 1.77% 0.31% Figure 8. CDFfor forthe the10 10min min voltage unbalance values values in the in the nanogrid nanogrid during during islanded islanded grid- and grid-connected operation. operation. Table 3. 95% confidence interval, the maximum 10 min value and total average value for all three 3.4. Voltage Fluctuations phases in islanded and grid-connected operation. The CDF of the Pst values for grid-connected and islanded operation can be seen in Figure 9. Operational State 95% CI 10 min Value Max 10 min Value Total Average Value The islanded operation data reaches lower Pst values than in grid-connected operation for 95% and 33% of the total Islanded measured time for 0.06 phase to 0.72% 2 and 1. Phase 3 has 4.6% larger Pst values 0.22% for the majority of the Grid-connected 0.11 to 0.68% 1.77% 0.31% time when comparing to the grid-connected operation Pst values. All three phases have higher maximum values than the grid-connected measurements. A summary of the 95% CI, maximum value and total average value for all three phases in islanded and grid-connected operation can be seen in Table 4. Table 4. 95% confidence interval, the maximum 10 min value and total average value for all three

9 Energies 2019, 12, of Voltage Fluctuations The CDF of the Pst values for grid-connected and islanded operation can be seen in Figure 9. Energies 2018, 11, x FOR PEER REVIEW 10 of 27 The islanded operation data reaches lower Pst values than in grid-connected operation for 95% and 33% of theoperational total measured time for phase 2 and 1. Phase 3 has larger Pst values for the majority of 95% CI Max Value Total Average Value the time when State comparing to the grid-connected operation Pst values. All three phases have higher maximum values Islanded than the grid-connected 0.06 to 0.74 measurements Ato summary 7 of the 95% 0.18 CI, to maximum 0.35 value and total Grid-connected average value for all0.14 three to phases 0.52 in islanded2.3 and to 2.34 grid-connected operation 0.24 to 0.32 can be seen in Table 4. Figure CDF for the Pst values for grid-connected and islanded operation where the interval 0 to 97.5% is displayed at the top andthe remaining upper 2.5% 2.5% is displayed in in the the bottom. bottom. The The black, black, red red and and blue blue color color represents phase phase 1 to 1 to3 3in in islanded mode. Purple color represents all three phases during grid-connected operation. Table 4. 95% confidence interval, the maximum 10 min value and total average value for all three The CDF of the Plt values for islanded and grid-connected operation can be seen in Figure 10. It phases in islanded and grid-connected operation. can be seen that phase 1 and 2 have lower Plt values for 91% and 35% of the total measured time in islanded operation Operational when State compared 95% to grid-connected CI Max operation. Value Total Phase Average 3 has Value lower Plt values for about 45% of the Islanded total measured time 0.06 tothan 0.74 the phase 6.43 to with 7 highest 0.18 Plt values to 0.35 in grid-connected operation. All three Grid-connected phases reach higher 0.14 to 0.52 maximum 2.3 Plt tovalues 2.34 in islanded 0.24 tooperation The 95% CI, maximum value and total average value can be seen in Table 5. The CDF of the Plt values for islanded and grid-connected operation can be seen in Figure 10. Table 5. 95% confidence interval, the maximum 10 min value and total average value for all three It can be seen that phase 1 and 2 have lower Plt values for 91% and 35% of the total measured time in phases in islanded and grid-connected operation. islanded operation when compared to grid-connected operation. Phase 3 has lower Plt values for about 45% ofoperational the total measured State time than 95% the CI phase withmaximum highest Plt Value values in grid-connected Total Average Value operation. All three phases Islanded reach higher maximum 0.07 to 0.72 Plt values in islanded 2.78 to operation The 95% 0.21 CI, to maximum 0.36 value and totalgrid-connected average value can be seen 0.19 to in0.52 Table to % 0.34

10 Energies 2019, 12, of 24 Energies 2018, 11, x FOR PEER REVIEW 11 of 27 Figure 10. CDF for the Plt values in grid-connected and islanded operation where the interval 0 to 97.5% is is displayedat atthe thetop topand andthe theremaining upper upper 2.5% 2.5% is displayed displayed in the in the bottom. bottom. The The black, black, red red and and blue blue color color represents represents phase phase 1 to 1 to 3 in 3 inislanded islandedmode. Purple Purplecolor representsall all three phases during grid-connected operation Table Voltage 5. 95% Variations confidence below interval, 10 Min thevalues maximum 10 min value and total average value for all three phases in islanded and grid-connected operation. The variations in the voltage that are on a shorter time scale than 10 min are calculated using the very short variations Operational (VSV) State of the voltage. 95% CI It was Maximum introduced Value by [10,11] Total Average to quantify Valuethe difference between very-short Islanded time scale (one 0.07 to several to 0.72 seconds) 2.78voltage to 2.99 RMS values 0.21 to and 0.36 the short time scale (10 min) voltage Grid-connected RMS value. The to min 0.52and 3 s 1.16 VSV to 1.2 values for grid-connected 0.26% 0.34 and islanded operation can be seen in Figure 11 where both the 10 min and 3 s VSV values are lower for the majority Voltage of the time Variations for islanded belowoperation. 10 Min Values The 3 s VSV values reach higher maximum values in islanded operation. A summary of the 95% CI, maximum values and total average value can be seen in Tables The variations in the voltage that are on a shorter time scale than 10 min are calculated using 6 and 7. the very short variations (VSV) of the voltage. It was introduced by [10,11] to quantify the difference between very-short time scale (one to several seconds) voltage RMS values and the short time scale Table 6. 95% confidence interval, the maximum 10 min value and total average value for all three (10 min) voltage RMS value. The 10 min and 3 s VSV values for grid-connected and islanded operation phases in islanded and grid-connected operation. can be seen in Figure 11 where both the 10 min and 3 s VSV values are lower for the majority of the time for islanded Operational operation. State The 95% 3 sci VSV 10 min values reach Max higher 10 min maximum Value values Total Average in islanded Value operation. A summary of Islanded the 95% CI, maximum to values 0.56 and total 4.6 average to 6.34 value can be seen into Tables and 7. Grid-connected 0.18 to to to 0.81 Table 6. 95% confidence interval, the maximum 10 min value and total average value for all three phases Table 7. in95% islanded confidence and grid-connected interval, the maximum operation. 3 s value and total average value for all three phases in islanded and grid-connected operation. Operational State 95% CI 10 min Max 10 min Value Total Average Value Operational State 95% CI 3 s Max 3 s Value Total Average Value Islanded to to to 0.15 Islanded 0 to to to 0.11 Grid-connected 0.18 to to to 0.81 Grid-connected to to to 0.66

11 Energies 2019, 12, of 24 Energies 2018, 11, x FOR PEER REVIEW 12 of 27 Figure CDF for for the the 10 min 10 min veryvery shortshort variations Variations (VSV) (VSV) values values (top) and (top) theand 3 s VSV the values 3 s VSV (bottom) values for (bottom) islanded for islanded grid-connected and grid-connected operation. operation. Table 7. 95% confidence interval, the maximum 3 s value and total average value for all three phases in 3.5. Neutral Current islanded and grid-connected operation. The CDF for the 10 min RMS neutral current for 48 weeks of islanded operation and 54 weeks Operational State 95% CI 3 s Max 3 s Value of grid-connected operation can be seen in Figure 12. Total Average Value Islanded 0 to to to 0.11 Grid-connected to to to Neutral Current The CDF for the 10 min RMS neutral current for 48 weeks of islanded operation and 54 weeks of grid-connected operation can be seen in Figure 12. The 50 Hz component was always several times larger than the zero sequence components where the 3rd harmonic reached a maximum value of 6 A during the 48 week measurement period in islanded operation. For both islanded and grid-connected operation, the line to neutral voltage was close to 0 V. The neutral current reached about the same maximum values of around 42 A in islanded and grid-connected operation. However, during islanded operation the 10 min values are for the most part higher than the grid-connected values. A summary of the 95% CI, maximum values and total average value can be seen in Table 8. Table 8. 95% confidence interval, the maximum 10 min value and total average value for all three phases in islanded and grid-connected operation. Operational State 95% CI 10 min Max 10 min Value Total Average Value Islanded 2.15 to Grid-connected 1.2 to Figure 12. CDF for the 10 min RMS neutral current during islanded and grid-connected operation.

12 Figure 11. CDF for the 10 min Very Short Variations (VSV) values (top) and the 3 s VSV values (bottom) for islanded and grid-connected operation Neutral Current The CDF for the 10 min RMS neutral current for 48 weeks of islanded operation and 54 weeks of grid-connected operation can be seen in Figure 12. Energies 2019, 12, of 24 Figure 12. CDF for the 10 min RMS neutral current during islanded and grid-connected operation. Figure 12. CDF for the 10 min RMS neutral current during islanded and grid-connected operation Operational Modes during Islanded Operation. The short circuit impedance is extracted from a 13 weeks continuous period. During this 13 week period, the nanogrid operated part of the time in islanded operation and part of the time in grid-connected operation, which can be seen in Figures The short circuit impedance was measured as the voltage drop against a current rise of larger than 4 A within two cycles. 4 A was chosen since values lower than 2 A could sometimes not affect the voltage, therefore a larger value of 4 A giving a 2 A margin was chosen. No correlation between the current rise magnitude (4 to 26 A in this paper) and the short circuit impedance were found and no correlation between the starting value of the current (0 to 36 A) and the short circuit impedance was found. In Figure 13 two different modes of islanded operation can be distinguished, one where the short circuit impedance fluctuates between 0.1 and 1 Ω and one in which it fluctuates between 0.1 and 2 Ω and sometimes reaching values close to 6 Ω but only for phase 2. During the grid-connected operation the values fluctuate between 0.2 and 0.4 Ω. The number of samples for the different phases was 31,000, 730 and 11,000 for phase 1 to 3 respectively, giving rise to differences in the horizontal axis in Figure 13. In Figures 14 16, the 10 min voltage THD, current THD, 3rd, 5th, 7th, 9th harmonic voltage and voltage unbalance are plotted for the 13 week period. The two different modes of islanded operation are again indicated. The voltage unbalance reaches the highest levels of about 4.6% during mode 2 of the islanded operation. The voltage THD, 3rd, 5th and 7th harmonic voltage is also larger in mode 2 for all three phases during the majority of the measured period. The 9th harmonic is for the most part lower in mode 2 for all three phases.

13 The short circuit impedance is extracted from a 13 weeks continuous period. During this 13 week period, the nanogrid operated part of the time in islanded operation and part of the time in gridconnected operation, which can be seen in Figure 13 to 16. The short circuit impedance was measured as the voltage drop against a current rise of larger than 4 A within two cycles. 4 A was chosen since values lower than 2 A could sometimes not affect the voltage, therefore a larger value of 4 A giving a 2 A margin was chosen. No correlation between the current rise magnitude (4 to 26 A in this paper) Energies 2019, 12, of 24 and the short circuit impedance were found and no correlation between the starting value of the current (0 to 36 A) and the short circuit impedance was found. Energies 2018, 11, x FOR PEER REVIEW 14 of 27 Figure 13. Short circuit impedance for 13 weeks of islanded and grid-connected measurements. The number of samples are around 31,000, 730 and 11,000 for phase 1 to 3 respectively. Note the difference in horizontal scale for each sub-plot. In Figure 13 two different modes of islanded operation can be distinguished, one where the short circuit impedance fluctuates between 0.1 and 1 Ω and one in which it fluctuates between 0.1 and 2 Ω and sometimes reaching values close to 6 Ω but only for phase 2. During the grid-connected operation the values fluctuate between 0.2 and 0.4 Ω. The number of samples for the different phases was 31,000, 730 and 11,000 for phase 1 to 3 respectively, giving rise to differences in the horizontal axis in Figure 13. In Figures 14 16, the 10 min voltage THD, current THD, 3rd, 5th, 7th, 9th harmonic voltage and voltage unbalance are plotted for the 13 week period. The two different modes of Figure islanded 13. Short operation circuit are impedance again indicated. for The 13 weeks voltage of unbalance islandedreaches grid-connected the highest levels measurements. of about 4.6% during mode 2 of the islanded operation. The voltage THD, 3rd, 5th and 7th harmonic voltage The number of samples are around 31,000, 730 and 11,000 for phase 1 to 3 respectively. Note the is also larger in mode 2 for all three phases during the majority of the measured period. The 9th difference harmonic in horizontal is for the most scale part forlower eachin sub-plot. mode 2 for all three phases. Figure 14. Figure The voltage 14. The voltage and current and current THD, THD, 3rd, 3rd, 5th, 5th, 7th, 9th harmonic voltage voltage and and voltage voltage unbalance unbalance for for phase 1 during a 13 week period in which the samples was extracted for a current rise larger than phase 1 during a 13 week period in which the samples was extracted for a current rise larger than 4 A 4 A within 2 cycles. within 2 cycles.

14 Energies 2019, 12, of 24 Energies 2018, 11, x FOR PEER REVIEW 15 of 27 Figure 15. The voltage and current THD, 3rd, 5th, 7th, 9th harmonic voltage and voltage unbalance for phase 2 during a 13 week period in which the samples was extracted for a current rise larger than 4 A Figure 15. The voltage and current THD, 3rd, 5th, 7th, 9th harmonic voltage and voltage unbalance for phase 2 during a 13 week period in which the samples was extracted for a current rise larger than 4 A within 2 cycles. within 2 cycles. Energies 2018, 11, x FOR PEER REVIEW 16 of 27 Figure 16. The Figure voltage 16. The and voltage current and current THD, THD, 3rd, 3rd, 5th, 5th, 7th, 7th, 9th harmonic voltage and and voltage voltage unbalance unbalance for for phase 3 during a 13 week period in which the samples was extracted for a current rise larger than phase 3 during a 13 week period in which the samples was extracted for a current rise larger than 4 A 4 A within 2 cycles. within 2 cycles. The average short circuit impedance for each hour during the day for around 8 weeks in islanded operation seen in Figure 13 can be seen in Figure 17. The blue and red line represents mode 1 and mode 2 respectively seen in Figure 13. The amount of samples for phase 1 to 3 is around 31,000, 730, 11,000 respectively, therefore phase 2 doesn t have samples for some hours during the day. It can be seen that the short circuit impedance is larger during the beginning of the day for phase 1 and larger during the middle of the day for phase 3. For phase 2 there are not enough samples to clearly see the

15 Energies 2019, 12, of 24 The average short circuit impedance for each hour during the day for around 8 weeks in islanded operation seen in Figure 13 can be seen in Figure 17. The blue and red line represents mode 1 and mode 2 respectively seen in Figure 13. The amount of samples for phase 1 to 3 is around 31,000, 730, 11,000 respectively, therefore phase 2 doesn t have samples for some hours during the day. It can be seen that the short circuit impedance is larger during the beginning of the day for phase 1 and larger during the middle of the day for phase 3. For phase 2 there are not enough samples to clearly see the variation during the day. However, for all three phases it can be seen that the short circuit impedance has a higher average for each hour during the day during mode 2 in islanded operation. Energies 2018, 11, x FOR PEER REVIEW 17 of 27 Figure The The average short short circuit circuit impedance impedance for each for each hour of hour the of daythe forday around for 8around weeks in 8 weeks islandedin operation islanded operation for Mode 1for and Mode Mode 1 and 2 seen Mode in Figure 2 seen 13. in Figure 13. The average values for each hour of the day for around 8 weeks in islanded operation for the 3rd to 9th odd harmonic voltages, currents and voltage THD for mode 1 in Figures can be seen in Figure 18. Mode 1 has larger 7th and 9th harmonic voltages and currents during the night for all three phases and the 5th harmonic has larger values for phase 1 and The 3rd harmonic is more evenly distributed across the day where the 3rd harmonic has larger average voltage and current values during the middle of the day. The voltage THD has the largest values during the night which corresponds with the result from the longer week measurements presented in in Figure 3. 3.

16 Energies 2019, 12, of 24 Energies 2018, 11, x FOR PEER REVIEW 18 of 27 (a) (b) Figure Figure (a) (a) The The odd odd harmonic voltage 3rd to 9th and THD for mode 1 in Figures (b) (b) The The odd odd harmonic current 3rd 3rd to to 9th 9th and and THD for mode 1 in Figures The average valuesare are grouped for for each each hour hour of of the the day day for for around 88 weeks of of islanded operation. Note alsothe the differencein in vertical scale scale for for the the different plots. plots. The The average values for for each hour during the day for around 8 weeksin in islanded operation for for the the 3rd 3rd to to 9th 9th odd odd harmonic voltages, currents and THDfor for mode mode 2 in 2 in Figures Figures can can be seen be seen in in Figure 19. The Theaverage 3rd 3rd harmonic harmonic voltage voltage is larger is larger during during the middle the middle of the day of the and day with and larger with larger magnitude magnitude than than in Figure in Figure The The 5th 5th and and 7th 7th harmonic harmonic has has the the largest largest voltage voltage distortion distortion levels levels during during the the night night for for all all 3 phases 3 phases and and larger larger variation variation between between night night and and day day in in comparison to to mode mode 1 seen 1 seen in Figure in Figure The The 9th 9th harmonic harmonic voltage voltage is is larger larger during during the the night night for for phase phase 3 3 and and higher higher during during the middle of the day for phase 1 and 2. The voltage THD has the largest values during the night the middle of the day for phase 1 and 2. The voltage THD has the largest values during the night which corresponds with the result from the longer 29 week measurements presented in Figure 3. The which corresponds with the result from the longer 29 week measurements presented in Figure 3. harmonic current levels follow the same pattern for some of the voltage harmonics but have opposite The harmonic current levels follow the same pattern for some of the voltage harmonics but have pattern for other voltage harmonics. This indicates that there are more factors that act on the voltage opposite pattern for other voltage harmonics. This indicates that there are more factors that act on the distortion than the current distortion. voltage distortion than the current distortion. In Figure 20, the 1 h average values are plotted for the 3rd and 5th harmonic current and voltage for around 8 weeks in islanded operation. The blue colored values are for mode 1 and the red colored values are for mode 2 seen in Figures The inclination (slope) corresponds to the impedance which is higher for mode 2 than for mode 1. However, for mode 1 the values form a more linear behavior than for mode 2. For the 3rd harmonic in phase 3, there is an appearance of a large area that has variation in voltage distortion without an increase in current distortion magnitude.

17 Energies 2019, 12, of 24 Energies 2018, 11, x FOR PEER REVIEW (a) 19 of 27 (b) Figure The harmonic odd harmonic voltage 3rdtoto9th 9th and and THD mode 2 in2figures (b) The(b) oddthe odd Figure 19. (a) 19. The(a)odd voltage 3rd THDforfor mode in Figures harmonic current 3rd to 9th and THD for mode 2 in Figures The average values are grouped harmonic current 3rd to 9th and THD for mode 2 in Figures The average values are grouped for each hour of the day for around 8 weeks of islanded operation. Note also the difference in vertical for eachscale hourforofthe thedifferent day forplots. around 8 weeks of islanded operation. Note also the difference in vertical scale for the different plots. Energies 2018, 11, x FOR PEER REVIEW 20 of 27 In Figure 20, the 1 h average values are plotted for the 3rd and 5th harmonic current and voltage for around 8 weeks in islanded operation. The blue colored values are for mode 1 and the red colored values are for mode 2 seen in Figures The inclination (slope) corresponds to the impedance which is higher for mode 2 than for mode 1. However, for mode 1 the values form a more linear behavior than for mode 2. For the 3rd harmonic in phase 3, there is an appearance of a large area that has variation in voltage distortion without an increase in current distortion magnitude. Another observation is that some of the measurements for mode 1 and 2 overlap each other which are expected since no criteria for the separation of the two modes exist except for the different time windows in Figures 13 to 16. (a) (b) 20.1(a) h 3rd harmonic voltage andcurrent current values plotted against each other forother Mode for 1 Mode 1 Figure 20. Figure (a) The hthe 3rd1harmonic voltage and values plotted against each and 2 seen in Figures (b) The 1 h 5th harmonic voltage and current values plotted against each and 2 seen in Figures (b) The 1 h 5th harmonic voltage and current values plotted against each other for Mode 1 and 2 seen in Figures other for Mode 1 and 2 seen in Figures In Figure 21, the 1 h values are plotted for the 7th and 9th harmonic current and voltage for all three phases for around 8 weeks in islanded operation. The blue colored values are mode 1 and the red colored values are for mode 2 seen in Figures The 7th and the 9th harmonic have some linear appearance for mode 1 but not as much as the 3rd and 5th harmonic. For mode 2 the behavior is more nonlinear, where some of the voltage distortion values are located close to zero current distortion for some phases. This indicates that the voltage distortion originates from the voltage source which is one of the possible sources of error in the impedance measurements. This is more

18 Energies 2019, 12, of 24 Another observation is that some of the measurements for mode 1 and 2 overlap each other which are expected since no criteria for the separation of the two modes exist except for the different time windows in Figures In Figure 21, the 1 h values are plotted for the 7th and 9th harmonic current and voltage for all three phases for around 8 weeks in islanded operation. The blue colored values are mode 1 and the red colored values are for mode 2 seen in Figures The 7th and the 9th harmonic have some linear appearance for mode 1 but not as much as the 3rd and 5th harmonic. For mode 2 the behavior is more nonlinear, where some of the voltage distortion values are located close to zero current distortion for some phases. This indicates that the voltage distortion originates from the voltage source which is one of the possible sources of error in the impedance measurements. This is more evident in the 9th harmonic than in the 7th harmonic. Energies 2018, 11, x FOR PEER REVIEW 21 of 27 (a) (b) Figure Figure (a) (a) The The 1 h1 h 7th 7th harmonic voltage and current values plotted against each other for for mode mode 1 1 and and 2 seen 2 seen in in Figures (b) (b) The 1 h 9th harmonic voltage and current values plotted against each each other other for for mode mode 1 and 1 and 2 seen 2 seen in in Figures Comparison 4. to to Reference Values In In this this section, some of of the measured values presented in Section3 3 are comparedto to the the European standard EN EN and and the the IEEE standard Voltage THD THD The The allowed min voltage THD for a low voltage networks is 8% for 95% of of the the time time per per week week for for both both IEEE IEEE standard and European standard EN IEEE standard has has also also a 12% a 12% THD THD limit limit for for 3 3 s values s for for 99% of of the time for one day at the low voltage Point of of Common Coupling (PCC). (PCC). During During islanded operation the the number of weeks that exceededthe the5% 5% allowedtime time frame frame in in which which the the min min voltage voltage THD THD could could be be above 8% is shown in inthe upperpart partof offigure Figure The The total total number of days that the 3 s voltage THD was over 12% for more than 1% of one day can also be seen in the upper part of Figure 22. The amount of time in which the voltage THD was over 8% and 12% can be seen in the lower part in Figure 22. Only phase 1 surpassed the 5% weekly limit for 8% voltage THD in EN and the 1% daily limit for 12% voltage THD described in IEEE During grid-connected operation no limits was surpassed.

19 Energies 2019, 12, of 24 number of days that the 3 s voltage THD was over 12% for more than 1% of one day can also be seen in the upper part of Figure 22. The amount of time in which the voltage THD was over 8% and 12% can be seen in the lower part in Figure 22. Only phase 1 surpassed the 5% weekly limit for 8% voltage THD in EN and the 1% daily limit for 12% voltage THD described in IEEE During grid-connected operation no limits was surpassed. Energies 2018, 11, x FOR PEER REVIEW 22 of 27 Figure 22. The number of times the voltage THD the limits in EN and IEEE Figure 22. The number of times the voltage THD exceeded the limits in EN and IEEE for the 10 min (in weeks) and 3 s (in days) (top) and the amount of time in which the voltage THD for the 10 min (in weeks) and 3 s (in days) (top) and the amount of time in which the voltage THD exceeded the 8% and 12% limits in EN and IEEE (bottom) for all three phases during exceeded the islanded 8% and operation. 12% limits The measurement in EN period and was IEEE 48 weeks (bottom) for all three phases during islanded operation. The measurement period was 48 weeks Individual Harmonics For 95% of the time during one week the 10 min value of the individual harmonics shall not go beyond the limits in Table 9 from EN For IEEE the limit for individual harmonics is 5% for 10 min values and 7.5% for 3 s values at a low voltage PCC Individual Harmonics For 95% of the time during one week the 10 min value of the individual harmonics shall not go beyond the limits in Table 9 from EN For IEEE the limit for individual harmonics is 5% for 10 min values and 7.5% for 3 s values at a low voltage PCC. Table 9. EN limits for individual harmonics at the low voltage Point of Common Coupling (PCC). Table 9. EN limits for individual Harmonic harmonics Order atpercent the lowof voltage Fund (%) Point of Common Coupling (PCC). 3rd 5 Harmonic Order 4th Percent 1 of Fund (%) 3rd 5th 6 6th th 7th 5 1 5th 8th th 9th th 11th th 0.5 8th 0.5 For both islanded and grid-connected 9th operation, the number 1.5 of weeks and total time in which the individual harmonics exceeded 11ththe limits in EN is shown in Figure 23. For islanded operation some individual harmonics 15th stays within the 5% allowed 0.5 time per week but exceed the limit sometime during the measurement period. Phase 2 during islanded operation never exceeds the 5% time limit. The 15th harmonic is only surpassed for one week for phase 3 during islanded operation. It can also be seen that the 9th harmonic exceeds almost every week for all three phases during islanded operation. For the grid-connected measurements, the 9th harmonic exceeded the 1.5% limit for 1 week. For both islanded and grid-connected operation, the number of weeks and total time in which the individual harmonics exceeded the limits in EN is shown in Figure 23. For islanded operation some individual harmonics stays within the 5% allowed time per week but exceed the limit sometime during the measurement period. Phase 2 during islanded operation never exceeds the 5% time limit. The 15th harmonic is only surpassed for one week for phase 3 during islanded operation. It can also be

20 Energies 2019, 12, of 24 seen that the 9th harmonic exceeds almost every week for all three phases during islanded operation. For the grid-connected measurements, the 9th harmonic exceeded the 1.5% limit for 1 week. Energies 2018, 11, x FOR PEER REVIEW 23 of 27 Energies 2018, 11, x FOR PEER REVIEW 23 of 27 Figure 23. The number of times the individual harmonics exceeded the 10 min limits in EN Figure 23. The number of times the individual harmonics exceeded the 10 min limits in EN (top) and the amount of time during the measurement period (48 weeks in islanded operation and 54 (top) and Figure the amount weeks in 23. grid-connected The number of time of during operation) times the the individual measurement which the harmonics period individual exceeded (48 harmonics the weeks 10 exceeded min in limits islanded the in limits EN operation in and EN 54 weeks (top) in and grid-connected (bottom) the amount for islanded of operation) time and during grid-connected the in which measurement the operation. individual period Note (48 the weeks harmonics logarithmic in islanded exceeded vertical operation scale. theand limits 54 in EN (bottom) weeks in for grid-connected islanded and operation) grid-connected in which the operation. individual Note harmonics the logarithmic exceeded the vertical limits in scale. EN The number (bottom) of for weeks islanded and amount grid-connected of time in operation. which the Note individual the logarithmic harmonics vertical exceeded scale. the limits in IEEE are shown in Figure 24. The number of weeks and amount of time in which the individual harmonics exceeded the limits in IEEE are shown in Figure 24. The number of weeks and amount of time in which the individual harmonics exceeded the limits in IEEE are shown in Figure 24. Figure 24. The number of times the individual harmonics exceeded the 10 min (in weeks) and 3 s limit (in days) in IEEE (top) and the amount of time during the measurement period of 48 weeks Figure in which 24. The the number individual of times harmonics the individual exceeded harmonics the limits exceeded in IEEE the min (in (bottom) weeks) for and islanded 3 s limit Figure 24. The number of times the individual harmonics exceeded the 10 min (in weeks) and 3 s limit (in operation. days) in IEEE (top) and the amount of time during the measurement period of 48 weeks (in days) in inwhich IEEEthe individual (top) harmonics and the amount exceeded of the time limits during IEEE the measurement (bottom) period for islanded of 48 weeks in which the operation. individual harmonics exceeded the limits in IEEE (bottom) for islanded operation.

21 Energies 2019, 2018, 12, 11, 614 x FOR PEER REVIEW of It can be seen that the 3rd, 5th and 7th harmonic are the only harmonics in the 10 min values It can be seen that the 3rd, 5th and 7th harmonic are the only harmonics in the 10 min values that exceed the 5% limit in IEEE during islanded operation. For the 3 s values the 3rd and that exceed the 5% limit in IEEE during islanded operation. For the s values the 3rd and 5th harmonics are the ones exceeding the 7.5% limit during islanded operation. The limits were not 5th harmonics are the ones exceeding the 7.5% limit during islanded operation. The limits were not surpassed during grid-connected operation. surpassed during grid-connected operation Long Term Flicker Severity 4.3. Long Term Flicker Severity In EN only the Plt value is specified which should be lower than 1 for 95% of the time for In EN only the Plt value is specified which should be lower than for 95% of the time for one week. For phase 1 and 3 the Plt value exceeded the limit for 3 weeks and phase 2 exceeded the one week. For phase 1 and 3 the Plt value exceeded the limit for 3 weeks and phase 2 exceeded the limit limit for 4 weeks. The grid-connected measurements never exceeded the 5% allowed time limit in EN for 4 weeks. The grid-connected measurements never exceeded the 5% allowed time limit in EN In Figure 25 the amount of time during the measurement period in which the Plt value exceeds In Figure 25 the amount of time during the measurement period in which the Plt value exceeds the the specified limit in EN for islanded and grid-connected is illustrated. The Plt values for specified limit in EN for islanded and grid-connected is illustrated. The Plt values for islanded islanded operation exceeded the limit in EN for about twice as long than in grid-connected operation exceeded the limit in EN for about twice as long than in grid-connected operation. operation. Figure 25. The number of of times the the Plt Plt values exceeded the the limits limits in in EN EN (top) (top) and and the the amount amount of time of time during during the the measurement period period of of weeks in in which the the Plt Plt values exceeded the limits in EN (bottom) for islanded operation Voltage Unbalance According to EN 50160the voltage unbalanceshould shouldnot not go go beyond beyond 2% 2% for for more more than than 5% 5% of the of the time time for for one one week. week. In the In the grid-connected grid-connected operation operation the the voltage voltage unbalance unbalance never never went went above above 2%. 2%. In In islanded islanded operation operation the the voltage voltage unbalancewent wentabove above2% 2% for for h, h, above 3% for 1.5 h in the 48 week measurements. The largest voltage unbalance during the longest consecutive time was 4.5% during 30 min. However, the voltage unbalance was kept below 2% for more than 95% of of each week. 5. Discussion 5. Discussion Effects on Equipment 5.1. Effects on Equipment It is stated in [12] that for a voltage THD between 8 and 10% motors could get overheated. It is stated in [12] that for a voltage THD between 8 and 10% motors could get overheated. The The measurements presented in Section 3 show that there can be levels that go beyond 8 and 10% measurements presented in Section 3 show that there can be levels that go beyond 8 and 10%

22 Energies 2019, 12, of 24 distortion in the nanogrid. This can lead to overheating for motors and other equipment sensitive to voltage harmonics. Flat topping of the voltage waveform can affect switched-mode power supplies since they need a high peak voltage to effectively charge its capacitor. Since the 10 min voltage THD values can reach up to 13% with up to 9.3% of 3rd harmonic content, equipment that has switched-mode power supplies could also suffer from excess heating. Especially harmonics 5 and 7 can also cause more losses in electrical motors and a counter electromotive force that leads to torque and vibration problems. Fluctuations in the voltage can affect several types of equipment (excluding flicker). One of those effects is accelerating or braking torques in motors, deterioration of electronic equipment in which the voltage fluctuations pass through the power supply to the electronic equipment such as computers, printers, control units, components for telecommunication [13,14]. In a production facility, these fluctuations could lead to variations in the speed of motors that cause unacceptable variations in production parameters such as color and diameter. There is no standard today that defines acceptable levels of VSV. Since the majority VSV values are lower in islanded operation than for grid-connected operation, there is an improvement of the performance in islanded operation when comparing to grid-connected operation. However, more research is needed before any conclusion can be drawn on how equipment will perform under high VSV values. The main effect of high Pst and Plt values is light flicker for incandescent lamps. Since the nanogrid only has LED lamps there could be either less or more light flicker depending on which LED lamp is used [15]. The difference in voltage flicker levels was larger between one phase and the other two phases for the majority of the time in islanded operation. This might suggest that the connected equipment might affect the flicker levels in a certain phase more in islanded operation than in grid operation since the flicker levels in the three phases during grid operation were closer to each other. The winding temperature increase in percent above rated temperature as a function of the voltage unbalance can be calculated from Equation (1) [16]: Temp rise = 2(Percent unbalance) 2 (1) From Equation (1) a temperature rise of 40.5% for 30 min could occur during the 48 week measurements for islanded operation. The maximum temperature rise would be 42.3% for 10 min. The average winding temperature increase for islanded operation is about 0.1% and about 0.2% for grid-connected operation. The reduction in lifetime of the motor due to temperature increase following the Arrhenius model is described in IEEE standard 101 [17]. Since the average winding temperature for a 3-phase motor is lower in islanded operation than in grid-connected operation, the lifetime of a 3-phase motor might increase in islanded operation. However, since there are times in which the motor can run on temperature elevations of up to 42.3% for shorter time periods at the same time as the voltage THD is above 8% (Mode 2 in Figure 14), a decrease in the lifetime of a motor could happen in comparison to grid-connected operation. 6. Conclusions The voltage THD and individual harmonics reach larger values in islanded operation than in grid-connected operation. The difference in magnitude between the phases is also larger in islanded operation. Figure 5 shows that the voltage THD increases during the evening without a change in load which suggests that the system impedance increases due to fewer parallel sources being active. This could be due to the shutdown of the solar inverter in the evening. The subsequent decrease in voltage harmonics levels in the morning could be caused by the activation of the solar inverter. During islanded operation the Pst and Plt values were lower for the majority of the time for phase 2 while the other two are for the majority of the time higher in islanded operation.

23 Energies 2019, 12, of 24 The 10 min and 3 s VSV value are for the majority of the time lower in islanded operation for all three phases. It can therefore be concluded that voltage variations on timescales 3 s to 10 min are lower in islanded operation. The voltage unbalance is lower for the majority of the time in islanded operation but could reach levels of over 4.5% for 30 consecutive minutes in islanded operation. Figures show that there are two modes of performance during islanded operation. Mode 2 operates with larger values of the short circuit impedance, voltage THD, voltage unbalance and individual voltage harmonics 3, 5, 7 for all three phases. For phase 3, the 9th harmonic voltage was also larger during mode 2. Mode 1 operates with a larger 9th harmonic voltage for phase 1 and 2. The 3rd harmonic impedance behaves almost linear in both modes and is larger during mode 2 for all three phases. The 5th harmonic impedance behaves more nonlinear but is generally larger during mode 2 for two phases. The 7th and 9th harmonic impedance show nonlinear behavior and no conclusion can be made regarding the magnitude of the harmonic impedance for the 7th and 9th harmonic. When the islanded operation was compared to the limits defined in grid standard EN it was found that the voltage THD, individual harmonics 3, 5, 6, 7, 9, 15, voltage unbalance and Plt limits were exceeded. For one week the 9th harmonic exceeded the limit during grid-connected operation. When the islanded operation was compared to the limits defined in grid standard IEEE it was found that the voltage THD, individual harmonics 3, 5, 7 were exceeded. The limits were not exceeded during grid-connected operation. More studies with long term measurements are needed to see if similar results are obtained for other nanogrids. Author Contributions: Conceptualization, J.N., S.K.R. and M.H.J.B.; Methodology, J.N.; Software, J.N.; Validation, J.N., S.K.R. and M.H.J.B.; Formal Analysis, J.N.; Investigation, J.N.; Resources, S.K.R. and M.H.J.B.; Data Curation, J.N.; Writing-Original Draft Preparation, J.N.; Writing-Review & Editing, J.N., S.K.R. and M.H.J.B.; Visualization, J.N.; Supervision, S.K.R. and M.H.J.B.; Project Administration, S.K.R. and M.H.J.B.; Funding Acquisition, S.K.R. and M.H.J.B. Funding: This paper has been funded by Skellefteå Kraft Elnät and Rönnbäret foundation. Conflicts of Interest: The authors declare no conflict of interest. References 1. Hatziargyriou, N. Microgrids Architectures and Control, 1st ed.; Wiley-IEEE Press: Hoboken, NJ, USA, 2014; pp Hatziargyriou, N.; Asano, H.; Iravani, R.; Marnay, C. Microgrids. IEEE Power Energy Mag. 2007, 5, [CrossRef] 3. CIGRÉ WG C6.22. Microgrids 1: Engineering, Economics, & Experience; The International Council on Large Electric Systems: Paris, France, Burmester, D.; Rayudu, R.; Seah, W.; Akinyele, D. A review of nanogrid topologies and technologies. Renew. Sustain. Energy Rev. 2017, 67, [CrossRef] 5. Cenelec Std. EN 50160:2010. Voltage Characteristics of Electricity Supplied by Public Electricity Networks; European Committee for Electrotechnical Standardization: Brussels, Belgium, IEEE Std IEEE Recommended Practice and Requirements for Harmonic Control in Electric Power Systems; IEEE Standards Association: Piscataway, NJ, USA, Nömm, J.; Rönnberg, S.K.; Bollen, M.H.J. An Analysis of Frequency Variations and its Implications on Connected Equipment for a Nanogrid during Islanded Operation. Energies 2018, 11, [CrossRef] 8. Rönnberg, S.K.; Bollen, M.H.J.; Nömm, J. Power Quality Measurements In a Single House Microgrid. In Proceedings of the CIRED 24th International Conference on Electricity Distribution, Glasgow, Scotland, UK, June 2017; pp

24 Energies 2019, 12, of Nömm, J.; Rönnberg, S.K.; Bollen, M.H.J. Harmonic Voltage measurements in a Single House Microgrid. In Proceedings of the ICHQP 18th International Conference on Harmonics and Quality of Power, Ljubljana, Slovenia, May 2018; pp Bollen, M.H.J.; Häger, M.; Schwaegerl, C. Quantifying voltage variations on a time scale between 3 seconds and 10 minutes. In Proceedings of the CIRED 18th International Conference and Exhibition on Electricity Distribution, Turin, Italy, 6 9 June 2005; pp Bollen, M.H.J.; Gu, I.Y.H. Characterization of voltage variations in the very-short time-scale. IEEE Trans. Power Deliv. 2005, 20, [CrossRef] 12. Dugan, R.C.; McGranaghan, M.F.; Santoso, S.; Beaty, H.W. Electrical Power System Quality, 2nd ed.; McGraw-Hill Education: New York, NY, USA, 2003; p Schlabbach, J.; Blume, D.; Stephanblome, T. Voltage Quality in Electrical Power Systems; The Institution of Electrical Engineers: Stevenage, UK, 2001; pp UIE WG 2. Guide to Quality of Electrical Supply for Industrial Installations, Part 5; Flicker and Voltage Fluctuations; International Union for Electricity Applications: Paris, France, 1999; p Gil-de-Castro, A.; Rönnberg, S.K.; Bollen, M.H.J. Light intensity variation (flicker) and harmonic emission related to LED lamps. Electr. Power Syst. Res. 2017, 146, [CrossRef] 16. Pillay, P.; Manyage, M. Derating of Induction Motors Operating With a Combination of Unbalanced Voltages and Over or Undervoltages. IEEE Trans. Energy Convers. 2002, 17, [CrossRef] 17. IEEE Std (R2010). Guide for the Statistical Analysis of Thermal Life Test Data; IEEE Standards Association: Piscataway, NJ, USA, by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (

Constant Terminal Voltage. Industry Workshop 1 st November 2013

Constant Terminal Voltage. Industry Workshop 1 st November 2013 Constant Terminal Voltage Industry Workshop 1 st November 2013 Covering; Reactive Power & Voltage Requirements for Synchronous Generators and how the requirements are delivered Other countries - A different

Læs mere

Wander TDEV Measurements for Inexpensive Oscillator

Wander TDEV Measurements for Inexpensive Oscillator Wander TDEV Measurements for Inexpensive Oscillator Lee Cosart Symmetricom Lcosart@symmetricom.com Geoffrey M. Garner SAMSUNG Electronics (Consultant) gmgarner@comcast.net IEEE 802.1 AVB TG 2009.11.02

Læs mere

Basic statistics for experimental medical researchers

Basic statistics for experimental medical researchers Basic statistics for experimental medical researchers Sample size calculations September 15th 2016 Christian Pipper Department of public health (IFSV) Faculty of Health and Medicinal Science (SUND) E-mail:

Læs mere

Linear Programming ١ C H A P T E R 2

Linear Programming ١ C H A P T E R 2 Linear Programming ١ C H A P T E R 2 Problem Formulation Problem formulation or modeling is the process of translating a verbal statement of a problem into a mathematical statement. The Guidelines of formulation

Læs mere

Statistical information form the Danish EPC database - use for the building stock model in Denmark

Statistical information form the Danish EPC database - use for the building stock model in Denmark Statistical information form the Danish EPC database - use for the building stock model in Denmark Kim B. Wittchen Danish Building Research Institute, SBi AALBORG UNIVERSITY Certification of buildings

Læs mere

Black Jack --- Review. Spring 2012

Black Jack --- Review. Spring 2012 Black Jack --- Review Spring 2012 Simulation Simulation can solve real-world problems by modeling realworld processes to provide otherwise unobtainable information. Computer simulation is used to predict

Læs mere

UNISONIC TECHNOLOGIES CO.,

UNISONIC TECHNOLOGIES CO., UNISONIC TECHNOLOGIES CO., 3 TERMINAL 1A NEGATIVE VOLTAGE REGULATOR DESCRIPTION 1 TO-263 The UTC series of three-terminal negative regulators are available in TO-263 package and with several fixed output

Læs mere

Basic Design Flow. Logic Design Logic synthesis Logic optimization Technology mapping Physical design. Floorplanning Placement Fabrication

Basic Design Flow. Logic Design Logic synthesis Logic optimization Technology mapping Physical design. Floorplanning Placement Fabrication Basic Design Flow System design System/Architectural Design Instruction set for processor Hardware/software partition Memory, cache Logic design Logic Design Logic synthesis Logic optimization Technology

Læs mere

Nyhedsmail, december 2013 (scroll down for English version)

Nyhedsmail, december 2013 (scroll down for English version) Nyhedsmail, december 2013 (scroll down for English version) Kære Omdeler Julen venter rundt om hjørnet. Og netop julen er årsagen til, at NORDJYSKE Distributions mange omdelere har ekstra travlt med at

Læs mere

On the complexity of drawing trees nicely: corrigendum

On the complexity of drawing trees nicely: corrigendum Acta Informatica 40, 603 607 (2004) Digital Object Identifier (DOI) 10.1007/s00236-004-0138-y On the complexity of drawing trees nicely: corrigendum Thorsten Akkerman, Christoph Buchheim, Michael Jünger,

Læs mere

Vina Nguyen HSSP July 13, 2008

Vina Nguyen HSSP July 13, 2008 Vina Nguyen HSSP July 13, 2008 1 What does it mean if sets A, B, C are a partition of set D? 2 How do you calculate P(A B) using the formula for conditional probability? 3 What is the difference between

Læs mere

Skriftlig Eksamen Kombinatorik, Sandsynlighed og Randomiserede Algoritmer (DM528)

Skriftlig Eksamen Kombinatorik, Sandsynlighed og Randomiserede Algoritmer (DM528) Skriftlig Eksamen Kombinatorik, Sandsynlighed og Randomiserede Algoritmer (DM58) Institut for Matematik og Datalogi Syddansk Universitet, Odense Torsdag den 1. januar 01 kl. 9 13 Alle sædvanlige hjælpemidler

Læs mere

RoE timestamp and presentation time in past

RoE timestamp and presentation time in past RoE timestamp and presentation time in past Jouni Korhonen Broadcom Ltd. 5/26/2016 9 June 2016 IEEE 1904 Access Networks Working Group, Hørsholm, Denmark 1 Background RoE 2:24:6 timestamp was recently

Læs mere

Privat-, statslig- eller regional institution m.v. Andet Added Bekaempelsesudfoerende: string No Label: Bekæmpelsesudførende

Privat-, statslig- eller regional institution m.v. Andet Added Bekaempelsesudfoerende: string No Label: Bekæmpelsesudførende Changes for Rottedatabasen Web Service The coming version of Rottedatabasen Web Service will have several changes some of them breaking for the exposed methods. These changes and the business logic behind

Læs mere

Unitel EDI MT940 June 2010. Based on: SWIFT Standards - Category 9 MT940 Customer Statement Message (January 2004)

Unitel EDI MT940 June 2010. Based on: SWIFT Standards - Category 9 MT940 Customer Statement Message (January 2004) Unitel EDI MT940 June 2010 Based on: SWIFT Standards - Category 9 MT940 Customer Statement Message (January 2004) Contents 1. Introduction...3 2. General...3 3. Description of the MT940 message...3 3.1.

Læs mere

TDC 4 Indoor voltage transformers

TDC 4 Indoor voltage transformers Medium Voltage Product TDC 4 Indoor voltage transformers Highest voltage for equipment [kv] 3.6-12 Power frequency test voltage, 1 min. [kv] 10 - Lightning impulse test voltage [kv] Max. rated burden,

Læs mere

applies equally to HRT and tibolone this should be made clear by replacing HRT with HRT or tibolone in the tibolone SmPC.

applies equally to HRT and tibolone this should be made clear by replacing HRT with HRT or tibolone in the tibolone SmPC. Annex I English wording to be implemented SmPC The texts of the 3 rd revision of the Core SPC for HRT products, as published on the CMD(h) website, should be included in the SmPC. Where a statement in

Læs mere

Project Step 7. Behavioral modeling of a dual ported register set. 1/8/ L11 Project Step 5 Copyright Joanne DeGroat, ECE, OSU 1

Project Step 7. Behavioral modeling of a dual ported register set. 1/8/ L11 Project Step 5 Copyright Joanne DeGroat, ECE, OSU 1 Project Step 7 Behavioral modeling of a dual ported register set. Copyright 2006 - Joanne DeGroat, ECE, OSU 1 The register set Register set specifications 16 dual ported registers each with 16- bit words

Læs mere

Gusset Plate Connections in Tension

Gusset Plate Connections in Tension Gusset Plate Connections in Tension Jakob Schmidt Olsen BSc Thesis Department of Civil Engineering 2014 DTU Civil Engineering June 2014 i Preface This project is a BSc project credited 20 ECTS points written

Læs mere

PARALLELIZATION OF ATTILA SIMULATOR WITH OPENMP MIGUEL ÁNGEL MARTÍNEZ DEL AMOR MINIPROJECT OF TDT24 NTNU

PARALLELIZATION OF ATTILA SIMULATOR WITH OPENMP MIGUEL ÁNGEL MARTÍNEZ DEL AMOR MINIPROJECT OF TDT24 NTNU PARALLELIZATION OF ATTILA SIMULATOR WITH OPENMP MIGUEL ÁNGEL MARTÍNEZ DEL AMOR MINIPROJECT OF TDT24 NTNU OUTLINE INEFFICIENCY OF ATTILA WAYS TO PARALLELIZE LOW COMPATIBILITY IN THE COMPILATION A SOLUTION

Læs mere

Trolling Master Bornholm 2012

Trolling Master Bornholm 2012 Trolling Master Bornholm 1 (English version further down) Tak for denne gang Det var en fornøjelse især jo også fordi vejret var med os. Så heldig har vi aldrig været før. Vi skal evaluere 1, og I må meget

Læs mere

Financial Literacy among 5-7 years old children

Financial Literacy among 5-7 years old children Financial Literacy among 5-7 years old children -based on a market research survey among the parents in Denmark, Sweden, Norway, Finland, Northern Ireland and Republic of Ireland Page 1 Purpose of the

Læs mere

Bookingmuligheder for professionelle brugere i Dansehallerne 2015-16

Bookingmuligheder for professionelle brugere i Dansehallerne 2015-16 Bookingmuligheder for professionelle brugere i Dansehallerne 2015-16 Modtager man økonomisk støtte til et danseprojekt, har en premieredato og er professionel bruger af Dansehallerne har man mulighed for

Læs mere

Vores mange brugere på musskema.dk er rigtig gode til at komme med kvalificerede ønsker og behov.

Vores mange brugere på musskema.dk er rigtig gode til at komme med kvalificerede ønsker og behov. På dansk/in Danish: Aarhus d. 10. januar 2013/ the 10 th of January 2013 Kære alle Chefer i MUS-regi! Vores mange brugere på musskema.dk er rigtig gode til at komme med kvalificerede ønsker og behov. Og

Læs mere

Bilag. Resume. Side 1 af 12

Bilag. Resume. Side 1 af 12 Bilag Resume I denne opgave, lægges der fokus på unge og ensomhed gennem sociale medier. Vi har i denne opgave valgt at benytte Facebook som det sociale medie vi ligger fokus på, da det er det største

Læs mere

BILAG 8.1.B TIL VEDTÆGTER FOR EXHIBIT 8.1.B TO THE ARTICLES OF ASSOCIATION FOR

BILAG 8.1.B TIL VEDTÆGTER FOR EXHIBIT 8.1.B TO THE ARTICLES OF ASSOCIATION FOR BILAG 8.1.B TIL VEDTÆGTER FOR ZEALAND PHARMA A/S EXHIBIT 8.1.B TO THE ARTICLES OF ASSOCIATION FOR ZEALAND PHARMA A/S INDHOLDSFORTEGNELSE/TABLE OF CONTENTS 1 FORMÅL... 3 1 PURPOSE... 3 2 TILDELING AF WARRANTS...

Læs mere

Generalized Probit Model in Design of Dose Finding Experiments. Yuehui Wu Valerii V. Fedorov RSU, GlaxoSmithKline, US

Generalized Probit Model in Design of Dose Finding Experiments. Yuehui Wu Valerii V. Fedorov RSU, GlaxoSmithKline, US Generalized Probit Model in Design of Dose Finding Experiments Yuehui Wu Valerii V. Fedorov RSU, GlaxoSmithKline, US Outline Motivation Generalized probit model Utility function Locally optimal designs

Læs mere

Bilag 8. TDC technical requirements for approval of splitterfilters and inline filters intended for shared access (ADSL or VDSL over POTS).

Bilag 8. TDC technical requirements for approval of splitterfilters and inline filters intended for shared access (ADSL or VDSL over POTS). Bilag 8. TDC technical requirements for approval of splitters and inline s intended for shared access (ADSL or VDSL over POTS). Dette bilag udgør bilag 8 til det mellem parterne tiltrådte Produkttillæg

Læs mere

Portal Registration. Check Junk Mail for activation . 1 Click the hyperlink to take you back to the portal to confirm your registration

Portal Registration. Check Junk Mail for activation  . 1 Click the hyperlink to take you back to the portal to confirm your registration Portal Registration Step 1 Provide the necessary information to create your user. Note: First Name, Last Name and Email have to match exactly to your profile in the Membership system. Step 2 Click on the

Læs mere

Brug sømbrættet til at lave sjove figurer. Lav fx: Få de andre til at gætte, hvad du har lavet. Use the nail board to make funny shapes.

Brug sømbrættet til at lave sjove figurer. Lav fx: Få de andre til at gætte, hvad du har lavet. Use the nail board to make funny shapes. Brug sømbrættet til at lave sjove figurer. Lav f: Et dannebrogsflag Et hus med tag, vinduer og dør En fugl En bil En blomst Få de andre til at gætte, hvad du har lavet. Use the nail board to make funn

Læs mere

X M Y. What is mediation? Mediation analysis an introduction. Definition

X M Y. What is mediation? Mediation analysis an introduction. Definition What is mediation? an introduction Ulla Hvidtfeldt Section of Social Medicine - Investigate underlying mechanisms of an association Opening the black box - Strengthen/support the main effect hypothesis

Læs mere

Dumped ammunition - an environmental problem for sediment management?

Dumped ammunition - an environmental problem for sediment management? 5th International SedNet Conference, 27th-29th May 2008, Oslo, Norway Dumped ammunition - an environmental problem for sediment management? Jens Laugesen, Det Norske Veritas Harald Bjørnstad, Forsvarsbygg

Læs mere

Measuring the Impact of Bicycle Marketing Messages. Thomas Krag Mobility Advice Trafikdage i Aalborg, 27.08.2013

Measuring the Impact of Bicycle Marketing Messages. Thomas Krag Mobility Advice Trafikdage i Aalborg, 27.08.2013 Measuring the Impact of Bicycle Marketing Messages Thomas Krag Mobility Advice Trafikdage i Aalborg, 27.08.2013 The challenge Compare The pilot pictures The choice The survey technique Only one picture

Læs mere

ME6212. High Speed LDO Regulators, High PSRR, Low noise, ME6212 Series. General Description. Typical Application. Package

ME6212. High Speed LDO Regulators, High PSRR, Low noise, ME6212 Series. General Description. Typical Application. Package High Speed LDO Regulators, High PSRR, Low noise, Series General Description The series are highly accurate, low noise, CMOS LDO Voltage Regulators. Offering low output noise, high ripple rejection ratio,

Læs mere

Learnings from the implementation of Epic

Learnings from the implementation of Epic Learnings from the implementation of Epic Appendix Picture from Region H (2016) A thesis report by: Oliver Metcalf-Rinaldo, oliv@itu.dk Stephan Mosko Jensen, smos@itu.dk Appendix - Table of content Appendix

Læs mere

CS 4390/5387 SOFTWARE V&V LECTURE 5 BLACK-BOX TESTING - 2

CS 4390/5387 SOFTWARE V&V LECTURE 5 BLACK-BOX TESTING - 2 1 CS 4390/5387 SOFTWARE V&V LECTURE 5 BLACK-BOX TESTING - 2 Outline 2 HW Solution Exercise (Equivalence Class Testing) Exercise (Decision Table Testing) Pairwise Testing Exercise (Pairwise Testing) 1 Homework

Læs mere

Evaluating Germplasm for Resistance to Reniform Nematode. D. B. Weaver and K. S. Lawrence Auburn University

Evaluating Germplasm for Resistance to Reniform Nematode. D. B. Weaver and K. S. Lawrence Auburn University Evaluating Germplasm for Resistance to Reniform Nematode D. B. Weaver and K. S. Lawrence Auburn University Major objectives Evaluate all available accessions of G. hirsutum (TX list) for reaction to reniform

Læs mere

Reexam questions in Statistics and Evidence-based medicine, august sem. Medis/Medicin, Modul 2.4.

Reexam questions in Statistics and Evidence-based medicine, august sem. Medis/Medicin, Modul 2.4. Reexam questions in Statistics and Evidence-based medicine, august 2013 2. sem. Medis/Medicin, Modul 2.4. Statistics : ESSAY-TYPE QUESTION 1. Intelligence tests are constructed such that the average score

Læs mere

Kvant Eksamen December 2010 3 timer med hjælpemidler. 1 Hvad er en continuous variable? Giv 2 illustrationer.

Kvant Eksamen December 2010 3 timer med hjælpemidler. 1 Hvad er en continuous variable? Giv 2 illustrationer. Kvant Eksamen December 2010 3 timer med hjælpemidler 1 Hvad er en continuous variable? Giv 2 illustrationer. What is a continuous variable? Give two illustrations. 2 Hvorfor kan man bedre drage konklusioner

Læs mere

The GAssist Pittsburgh Learning Classifier System. Dr. J. Bacardit, N. Krasnogor G53BIO - Bioinformatics

The GAssist Pittsburgh Learning Classifier System. Dr. J. Bacardit, N. Krasnogor G53BIO - Bioinformatics The GAssist Pittsburgh Learning Classifier System Dr. J. Bacardit, N. Krasnogor G53BIO - Outline bioinformatics Summary and future directions Objectives of GAssist GAssist [Bacardit, 04] is a Pittsburgh

Læs mere

Varenr.: 553925 90 højre 553926 90 venstre 554027 90º højre med coating 554028 90º venstre med coating

Varenr.: 553925 90 højre 553926 90 venstre 554027 90º højre med coating 554028 90º venstre med coating DK GH Skiftespor Varenr.: 55395 90 højre 55396 90 venstre 55407 90º højre med coating 55408 90º venstre med coating 553991 60º højre 553995 60º venstre 551058 60º højre med coating 551059 60º venstre med

Læs mere

Tidevandstabeller for danske farvande. Tide tables for Danish waters

Tidevandstabeller for danske farvande. Tide tables for Danish waters devandstabeller for danske farvande de tables for anish waters 0 Indhold ontents - orklaring til tabeller Explanation of tables Havnefortegnelse ist of ports - Tabeller for høj- og lavvandstidspunkter

Læs mere

ATEX direktivet. Vedligeholdelse af ATEX certifikater mv. Steen Christensen stec@teknologisk.dk www.atexdirektivet.

ATEX direktivet. Vedligeholdelse af ATEX certifikater mv. Steen Christensen stec@teknologisk.dk www.atexdirektivet. ATEX direktivet Vedligeholdelse af ATEX certifikater mv. Steen Christensen stec@teknologisk.dk www.atexdirektivet.dk tlf: 7220 2693 Vedligeholdelse af Certifikater / tekniske dossier / overensstemmelseserklæringen.

Læs mere

Lithium-Ion Jump-Starters / Jumper Cables

Lithium-Ion Jump-Starters / Jumper Cables AUTOMOTIVE Lithium-Ion Jump-Starters / Jumper Cables Lithium-Ion Jump-Starter 1300: Part No. DRLJS130 1300 4 6 8 cylinder (6 liter gas 3 liter diesel) SafeJump technology prevents sparking and protects

Læs mere

Filtering on Wires Cable Ferrites, Usage & Comparison Alex Snijder Field Application Engineer Wurth Elektronik Nederland B.V.

Filtering on Wires Cable Ferrites, Usage & Comparison Alex Snijder Field Application Engineer Wurth Elektronik Nederland B.V. Filtering on Wires Cable Ferrites, Usage & Comparison Alex Snijder Field Application Engineer Wurth Elektronik Nederland B.V. Agenda Electromagnetic Compatibility (EMC) Application of Cable Ferrites Impedance

Læs mere

Central Statistical Agency.

Central Statistical Agency. Central Statistical Agency www.csa.gov.et 1 Outline Introduction Characteristics of Construction Aim of the Survey Methodology Result Conclusion 2 Introduction Meaning of Construction Construction may

Læs mere

Small Autonomous Devices in civil Engineering. Uses and requirements. By Peter H. Møller Rambøll

Small Autonomous Devices in civil Engineering. Uses and requirements. By Peter H. Møller Rambøll Small Autonomous Devices in civil Engineering Uses and requirements By Peter H. Møller Rambøll BACKGROUND My Background 20+ years within evaluation of condition and renovation of concrete structures Last

Læs mere

Analyseinstitut for Forskning

Analyseinstitut for Forskning Analyseinstitut for Forskning CIS3 The Danish Non-response Analysis Peter S. Mortensen Notat 2003/1 fra Analyseinstitut for Forskning The Danish Institute for Studies in Research and Research Policy Finlandsgade

Læs mere

Sign variation, the Grassmannian, and total positivity

Sign variation, the Grassmannian, and total positivity Sign variation, the Grassmannian, and total positivity arxiv:1503.05622 Slides available at math.berkeley.edu/~skarp Steven N. Karp, UC Berkeley FPSAC 2015 KAIST, Daejeon Steven N. Karp (UC Berkeley) Sign

Læs mere

Trolling Master Bornholm 2016 Nyhedsbrev nr. 5

Trolling Master Bornholm 2016 Nyhedsbrev nr. 5 Trolling Master Bornholm 2016 Nyhedsbrev nr. 5 English version further down Kim Finne med 11 kg laks Laksen blev fanget i denne uge øst for Bornholm ud for Nexø. Et andet eksempel er her to laks taget

Læs mere

Elektriske apparater til husholdningsbrug o.l. Sikkerhed Del 1: Generelle krav

Elektriske apparater til husholdningsbrug o.l. Sikkerhed Del 1: Generelle krav Dansk standard Tillæg DS/IEC 60335-1/A1:2013 + Corr 1:2014 1. udgave 2014-05-08 Elektriske apparater til husholdningsbrug o.l. Sikkerhed Del 1: Generelle krav Household and similar electrical appliances

Læs mere

The X Factor. Målgruppe. Læringsmål. Introduktion til læreren klasse & ungdomsuddannelser Engelskundervisningen

The X Factor. Målgruppe. Læringsmål. Introduktion til læreren klasse & ungdomsuddannelser Engelskundervisningen The X Factor Målgruppe 7-10 klasse & ungdomsuddannelser Engelskundervisningen Læringsmål Eleven kan give sammenhængende fremstillinger på basis af indhentede informationer Eleven har viden om at søge og

Læs mere

Aktivering af Survey funktionalitet

Aktivering af Survey funktionalitet Surveys i REDCap REDCap gør det muligt at eksponere ét eller flere instrumenter som et survey (spørgeskema) som derefter kan udfyldes direkte af patienten eller forsøgspersonen over internettet. Dette

Læs mere

Slot diffusers. Slot diffusers LD-17, LD-18

Slot diffusers. Slot diffusers LD-17, LD-18 LD-17, LD-18 Application LD-17 and LD-18 are designed for supply of cold or warm air in rooms with a height between. m and 4 m. They allow easy setting of air deflectors for different modes of operation

Læs mere

User Manual for LTC IGNOU

User Manual for LTC IGNOU User Manual for LTC IGNOU 1 LTC (Leave Travel Concession) Navigation: Portal Launch HCM Application Self Service LTC Self Service 1. LTC Advance/Intimation Navigation: Launch HCM Application Self Service

Læs mere

Help / Hjælp

Help / Hjælp Home page Lisa & Petur www.lisapetur.dk Help / Hjælp Help / Hjælp General The purpose of our Homepage is to allow external access to pictures and videos taken/made by the Gunnarsson family. The Association

Læs mere

Name: Week of April 1 MathWorksheets.com

Name: Week of April 1 MathWorksheets.com Get a fidget spinner! Spin it. I needed to spin time(s) to finish. Find the GCF using the Birthday Cake method. 5 45 55 9 11 5 = 5 4 16 12 2 14 12 5 100 50 3 15 27 80 208 240 144 70 45 21 24 45 57 Spin

Læs mere

Dendrokronologisk Laboratorium

Dendrokronologisk Laboratorium Dendrokronologisk Laboratorium NNU rapport 8, 2001 BRO OVER SKJERN Å, RINGKØBING AMT Skjern Å Projektet/Oxbøl Statsskovdistrikt/RAS. Indsendt af Torben Egeberg og Mogens Schou Jørgensen. Undersøgt af Aoife

Læs mere

De tre høringssvar findes til sidst i dette dokument (Bilag 1, 2 og 3). I forlængelse af de indkomne kommentarer bemærkes følgende:

De tre høringssvar findes til sidst i dette dokument (Bilag 1, 2 og 3). I forlængelse af de indkomne kommentarer bemærkes følgende: NOTAT VEDR. HØRINGSSVAR København 2018.10.26 BAGGRUND: Kommunalbestyrelsen i Frederiksberg Kommune vedtog den 18. april 2016 at igangsætte processen omkring etablering af et fælles gårdanlæg i karré 41,

Læs mere

To the reader: Information regarding this document

To the reader: Information regarding this document To the reader: Information regarding this document All text to be shown to respondents in this study is going to be in Danish. The Danish version of the text (the one, respondents are going to see) appears

Læs mere

Web-seminar. 30 March Noter

Web-seminar. 30 March Noter Web-seminar 30 March 2017 Noter Følg mig på www.tomhougaard.dk Hvad er Day Trading og Spekulation? Attachment is the great fabricator of illusions; reality can be attained only by someone who is detached.

Læs mere

TM4 Central Station. User Manual / brugervejledning K2070-EU. Tel Fax

TM4 Central Station. User Manual / brugervejledning K2070-EU. Tel Fax TM4 Central Station User Manual / brugervejledning K2070-EU STT Condigi A/S Niels Bohrs Vej 42, Stilling 8660 Skanderborg Denmark Tel. +45 87 93 50 00 Fax. +45 87 93 50 10 info@sttcondigi.com www.sttcondigi.com

Læs mere

Trolling Master Bornholm 2016 Nyhedsbrev nr. 8

Trolling Master Bornholm 2016 Nyhedsbrev nr. 8 Trolling Master Bornholm 2016 Nyhedsbrev nr. 8 English version further down Der bliver landet fisk men ikke mange Her er det Johnny Nielsen, Søløven, fra Tejn, som i denne uge fangede 13,0 kg nord for

Læs mere

Trolling Master Bornholm 2014

Trolling Master Bornholm 2014 Trolling Master Bornholm 2014 (English version further down) Den ny havn i Tejn Havn Bornholms Regionskommune er gået i gang med at udvide Tejn Havn, og det er med til at gøre det muligt, at vi kan være

Læs mere

Tidevandstabeller for danske farvande. Tide tables for Danish waters

Tidevandstabeller for danske farvande. Tide tables for Danish waters devandstabeller for danske farvande de tables for anish waters Indhold ontents - orklaring til tabeller Explanation of tables Havnefortegnelse ist of ports - Tabeller for høj- og lavvandstidspunkter samt

Læs mere

LED STAR PIN G4 BASIC INFORMATION: Series circuit. Parallel circuit. www.osram.com 1. HOW CAN I UNDERSTAND THE FOLLOWING SHEETS?

LED STAR PIN G4 BASIC INFORMATION: Series circuit. Parallel circuit. www.osram.com 1. HOW CAN I UNDERSTAND THE FOLLOWING SHEETS? BASIC INFORMATION: 1. HOW CAN I UNDERSTAND THE FOLLOWING SHES? Compatibility to OSRAM s: -Series Circuit... Page 2 -Parallel Circuit... Page 3 Compatibility to OTHER s : -Series Circuit... Page 4 -Parallel

Læs mere

DSB s egen rejse med ny DSB App. Rubathas Thirumathyam Principal Architect Mobile

DSB s egen rejse med ny DSB App. Rubathas Thirumathyam Principal Architect Mobile DSB s egen rejse med ny DSB App Rubathas Thirumathyam Principal Architect Mobile Marts 2018 AGENDA 1. Ny App? Ny Silo? 2. Kunden => Kunderne i centrum 1 Ny app? Ny silo? 3 Mødetitel Velkommen til Danske

Læs mere

Statistik for MPH: 7

Statistik for MPH: 7 Statistik for MPH: 7 3. november 2011 www.biostat.ku.dk/~pka/mph11 Attributable risk, bestemmelse af stikprøvestørrelse (Silva: 333-365, 381-383) Per Kragh Andersen 1 Fra den 6. uges statistikundervisning:

Læs mere

The River Underground, Additional Work

The River Underground, Additional Work 39 (104) The River Underground, Additional Work The River Underground Crosswords Across 1 Another word for "hard to cope with", "unendurable", "insufferable" (10) 5 Another word for "think", "believe",

Læs mere

Resource types R 1 1, R 2 2,..., R m CPU cycles, memory space, files, I/O devices Each resource type R i has W i instances.

Resource types R 1 1, R 2 2,..., R m CPU cycles, memory space, files, I/O devices Each resource type R i has W i instances. System Model Resource types R 1 1, R 2 2,..., R m CPU cycles, memory space, files, I/O devices Each resource type R i has W i instances. Each process utilizes a resource as follows: request use e.g., request

Læs mere

CHAPTER 8: USING OBJECTS

CHAPTER 8: USING OBJECTS Ruby: Philosophy & Implementation CHAPTER 8: USING OBJECTS Introduction to Computer Science Using Ruby Ruby is the latest in the family of Object Oriented Programming Languages As such, its designer studied

Læs mere

NOTIFICATION. - An expression of care

NOTIFICATION. - An expression of care NOTIFICATION - An expression of care Professionals who work with children and young people have a special responsibility to ensure that children who show signs of failure to thrive get the wright help.

Læs mere

DoodleBUGS (Hands-on)

DoodleBUGS (Hands-on) DoodleBUGS (Hands-on) Simple example: Program: bino_ave_sim_doodle.odc A simulation example Generate a sample from F=(r1+r2)/2 where r1~bin(0.5,200) and r2~bin(0.25,100) Note that E(F)=(100+25)/2=62.5

Læs mere

TMC - Klima

TMC - Klima NOTAT TMC Klima 97218 CO 2regnskab 217 Ifølge HøjeTaastrup Kommunes KlimaKommuneaftale med Danmarks Naturfredningsforening skal der udarbejdes og offentliggøres et årligt regnskab over kommunens CO 2 udledning.

Læs mere

Sport for the elderly

Sport for the elderly Sport for the elderly - Teenagers of the future Play the Game 2013 Aarhus, 29 October 2013 Ditte Toft Danish Institute for Sports Studies +45 3266 1037 ditte.toft@idan.dk A growing group in the population

Læs mere

Trolling Master Bornholm 2016 Nyhedsbrev nr. 7

Trolling Master Bornholm 2016 Nyhedsbrev nr. 7 Trolling Master Bornholm 2016 Nyhedsbrev nr. 7 English version further down Så var det omsider fiskevejr En af dem, der kom på vandet i en af hullerne, mellem den hårde vestenvind var Lejf K. Pedersen,

Læs mere

BILAG 8.1.F TIL VEDTÆGTER FOR EXHIBIT 8.1.F TO THE ARTICLES OF ASSOCIATION FOR

BILAG 8.1.F TIL VEDTÆGTER FOR EXHIBIT 8.1.F TO THE ARTICLES OF ASSOCIATION FOR BILAG 8.1.F TIL VEDTÆGTER FOR ZEALAND PHARMA A/S EXHIBIT 8.1.F TO THE ARTICLES OF ASSOCIATION FOR ZEALAND PHARMA A/S INDHOLDSFORTEGNELSE/TABLE OF CONTENTS 1 FORMÅL... 3 1 PURPOSE... 3 2 TILDELING AF WARRANTS...

Læs mere

Special VFR. - ved flyvning til mindre flyveplads uden tårnkontrol som ligger indenfor en kontrolzone

Special VFR. - ved flyvning til mindre flyveplads uden tårnkontrol som ligger indenfor en kontrolzone Special VFR - ved flyvning til mindre flyveplads uden tårnkontrol som ligger indenfor en kontrolzone SERA.5005 Visual flight rules (a) Except when operating as a special VFR flight, VFR flights shall be

Læs mere

HA-SPAD MEDIA KIT

HA-SPAD MEDIA KIT HA-SPAD0223185808 2017 MEDIA KIT 147,912 1,064,820 WITH 55.6% MOBILE 3.76 (4.24 MOBILE) Source: Omniture Nov. 16 - Jan 17; Nielsen PRIZM 2015, Compete June 2014 - June 2015 Average USA Today Cars.com

Læs mere

Trolling Master Bornholm 2014

Trolling Master Bornholm 2014 Trolling Master Bornholm 2014 (English version further down) Populært med tidlig færgebooking Booking af færgebilletter til TMB 2014 er populært. Vi har fået en stribe mails fra teams, som har booket,

Læs mere

Bachelorprojekt. Forår 2013 DMD10

Bachelorprojekt. Forår 2013 DMD10 + Bachelorprojekt Forår 2013 DMD10 +! 1. Om at skrive bachelorprojekt! 2. Typer af bachelorprojekter! 3. To eksempler på DMD-projekter! 4. Overvejelser over samarbejdsformer, proces, sprog! 5. ITUs generelle

Læs mere

Accessing the ALCOTEST Instrument Upload Data - NJSP Public Website page -

Accessing the ALCOTEST Instrument Upload Data - NJSP Public Website page - Accessing the ALCOTEST Instrument Upload Data - NJSP Public Website page - www.njsp.org Public Information Access Public Information Page Selection Within the Public Information Drop Down list, select

Læs mere

E-PAD Bluetooth hængelås E-PAD Bluetooth padlock E-PAD Bluetooth Vorhängeschloss

E-PAD Bluetooth hængelås E-PAD Bluetooth padlock E-PAD Bluetooth Vorhängeschloss E-PAD Bluetooth hængelås E-PAD Bluetooth padlock E-PAD Bluetooth Vorhängeschloss Brugervejledning (side 2-6) Userguide (page 7-11) Bedienungsanleitung 1 - Hvordan forbinder du din E-PAD hængelås med din

Læs mere

An expression of care Notification. Engelsk

An expression of care Notification. Engelsk An expression of care Notification Engelsk Kolding Kommune Senior- og Socialforvaltningen, Familierådgivningen Professionals who work with children and young have a special responsibility to ensure that

Læs mere

QUICK START Updated:

QUICK START Updated: QUICK START Updated: 24.08.2018 For at komme hurtigt og godt igang med dine nye Webstech produkter, anbefales at du downloader den senest opdaterede QuickStart fra vores hjemmeside: In order to get started

Læs mere

Last Lecture CS Amp. I D V B M 2. I bias. A v. V out. V in. Simplified Schematic. Practical Implementation V GS

Last Lecture CS Amp. I D V B M 2. I bias. A v. V out. V in. Simplified Schematic. Practical Implementation V GS Output Range INEL 565 Analog Circuit Design 1/30/019 Last Lecture CS Amp. I D off ohmic sat sat ohmic ohmic I bias V B I bias V dd V dd -V ov A v Simplified Schematic Practical Implementation V ov1 V th

Læs mere

Nyhedsmail, november 2013 (scroll down for English version)

Nyhedsmail, november 2013 (scroll down for English version) Nyhedsmail, november 2013 (scroll down for English version) Kære Omdeler Uret er stillet til vintertid, og antallet af lyse timer i døgnet er fortsat faldende. Vintermørket er kort sagt over os, og det

Læs mere

Dendrokronologisk Laboratorium

Dendrokronologisk Laboratorium Dendrokronologisk Laboratorium NNU rapport 14, 2001 ROAGER KIRKE, TØNDER AMT Nationalmuseet og Den Antikvariske Samling i Ribe. Undersøgt af Orla Hylleberg Eriksen. NNU j.nr. A5712 Foto: P. Kristiansen,

Læs mere

Molio specifications, development and challenges. ICIS DA 2019 Portland, Kim Streuli, Molio,

Molio specifications, development and challenges. ICIS DA 2019 Portland, Kim Streuli, Molio, Molio specifications, development and challenges ICIS DA 2019 Portland, Kim Streuli, Molio, 2019-06-04 Introduction The current structure is challenged by different factors. These are for example : Complex

Læs mere

Handling Sporadic Tasks in Off- Line Scheduled Distributed Real Time Systems

Handling Sporadic Tasks in Off- Line Scheduled Distributed Real Time Systems Handling Sporadic Tasks in Off- Line Scheduled Distributed Real Time Systems Damir Isović & Gerhard Fohler Department of Computer Engineering Mälardalen University, Sweden Presented by : Aseem Lalani Outline

Læs mere

November hilsner fra NORDJYSKE Medier, Distributionen

November hilsner fra NORDJYSKE Medier, Distributionen Uret er stillet til vintertid, og det betyder, at der nu er mørkt både morgen og aften. Det er vigtigt, at du er synlig i trafikken i vintermørket, og derfor opfordrer vi dig til at bruge din refleksvest,

Læs mere

DET KONGELIGE BIBLIOTEK NATIONALBIBLIOTEK OG KØBENHAVNS UNIVERSITETS- BIBLIOTEK. Index

DET KONGELIGE BIBLIOTEK NATIONALBIBLIOTEK OG KØBENHAVNS UNIVERSITETS- BIBLIOTEK. Index DET KONGELIGE Index Download driver... 2 Find the Windows 7 version.... 2 Download the Windows Vista driver.... 4 Extract driver... 5 Windows Vista installation of a printer.... 7 Side 1 af 12 DET KONGELIGE

Læs mere

Green Passenger Ferries

Green Passenger Ferries - Your professional maritime partner Faaborg Værft A/S Værftsvej 7, DK-5600 Faaborg, Tlf: +45 62 61 21 10 www.faaborg-vaerft.dk, fv@faaborg-vaerft.dk Sjövägen delivered to Ballerina AB located in Stockholm,

Læs mere

Dendrokronologisk Laboratorium

Dendrokronologisk Laboratorium Dendrokronologisk Laboratorium NNU rapport 5, 1997 STRANDGADE 3A, KØBENHAVN Nationalmuseets Marinarkæologiske Undersøgelser. Indsendt af Christian Lemée. Undersøgt af Aoife Daly og Niels Bonde. NNU j.nr.

Læs mere

GNSS/INS Product Design Cycle. Taking into account MEMS-based IMU sensors

GNSS/INS Product Design Cycle. Taking into account MEMS-based IMU sensors GNSS/INS Product Design Cycle Taking into account MEMS-based IMU sensors L. Vander Kuylen 15 th th December 2005 Content Product Definition Product Development Hardware Firmware Measurement Campaign in

Læs mere

SKEMA TIL AFRAPPORTERING EVALUERINGSRAPPORT

SKEMA TIL AFRAPPORTERING EVALUERINGSRAPPORT SKEMA TIL AFRAPPORTERING EVALUERINGSRAPPORT OBS! Excel-ark/oversigt over fagelementernes placering i A-, B- og C-kategorier skal vedlægges rapporten. - Følgende bedes udfyldt som del af den Offentliggjorte

Læs mere

Sikkerhedsvejledning

Sikkerhedsvejledning 11-01-2018 2 Sikkerhedsvejledning VIGTIGT! Venligst læs disse instruktioner inden sengen samles og tages i brug Tjek at alle dele og komponenter er til stede som angivet i vejledningen Fjern alle beslagsdele

Læs mere

Engelsk. Niveau D. De Merkantile Erhvervsuddannelser September Casebaseret eksamen. og

Engelsk. Niveau D. De Merkantile Erhvervsuddannelser September Casebaseret eksamen.  og 052431_EngelskD 08/09/05 13:29 Side 1 De Merkantile Erhvervsuddannelser September 2005 Side 1 af 4 sider Casebaseret eksamen Engelsk Niveau D www.jysk.dk og www.jysk.com Indhold: Opgave 1 Presentation

Læs mere

talk outline sea bed network deployment issues; energy distribution seabed network issues;

talk outline sea bed network deployment issues; energy distribution seabed network issues; talk outline sea bed network deployment issues; energy distribution seabed network issues; data transmission seabed network; seabed network decisional process specification from physics no deployment feasibility

Læs mere

Skidding System. Challenge Us

Skidding System. Challenge Us Skidding System n Malm Orstads cutting edge Engineering department designs and fabricates tailor made skidding systems for all kinds of enviroments. Our skidding systems are amongst the most efficient

Læs mere