DATO DOKUMENT SAGSBEHANDLER MAIL TELEFON 4. oktober 2012 11/12993 Thomas Lind Hansen thoh@vd.dk 7244 2727 Belysning - Vejbelysningsskabe Bilag D2 - Type 3 - Montage- og installationsvejledning, 2012.10.04 Teglgårdsparken 102 5500 Middelfart vd@vd.dk EAN 5798000893450 Telefon 7244 2200 vejdirektoratet.dk SE 60729018
INDHOLDSFORTEGNELSE INDHOLDSFORTEGNELSE... 1 OPSTILLING AF FUNDAMENT... 2 EFTER MONTERING AF LÅGE... 3 KABELFORSKRUNINGER... 4 MONTERING AF TILGANG... 5 BATTERI... 7 AUTOTRANSFORMER... 8 TIMER.... 9 AFPRØVNING OG IDRIFTSÆTNING... 10 KONTAKTOPLYSNINGER TIL LEVERANDØR:... 11 BILAG 1 : PRINCIP FOR FUNDERING AF VEJBELYSNINGSSKABE... 12 1 / 12
OPSTILLING AF FUNDAMENT SOKKEL NEDGRAVES TIL MARKERET LINIE. SOKKEL NEDGRAVES HER TIL! OPSTILLING AF FUNDAMENT: UDGRAVNING UDFØRES I PASSENDE STØRRELSE. UDGRAVNINGEN SKAL VÆRE SÅ STOR, AT DER KAN FORETAGES KOMPRIMERING AF FYLDMATERIALET UDEN AT FUNDAMENT BESKADIGES. BUNDEN AFRETTES OG KOMPRIMERES MED MIN. 50 MM JORDFUGTIG BETON, OG SKABETS FUNDAMENT OPSTILLES I KORREKT HØJDE. KABLER OPFØRES TRUKKET I KABELRØR OG UDGRAVNING TILFYLDES MED STABILGRUS SOM KOMPRIMERES LAGVIS EFTER HVER 200 MM. SÅFREMT VEJBELYSNINGSSKABET PLACERES I IKKE BEFÆSTET AREAL SKAL DER ETABLERES BETON FLISEBELÆGNING I FUNDAMENTETS BREDDE OG 1200 MM UD FRA FUNDAMENTET FORAN SKABETS LÅGER. SE BILAG 1 2 / 12
LÅGEN FASTMONTERES MED BOLTE EFTER MONTERING AF LÅGE 3 / 12
KABELFORSKRUNINGER HER ISÆTTES KABELFORSKRUNNINGER I INDRE KAPSLING HER ISÆTTES KABELFORSKRUNINGER I YDRE KAPSLING 4 / 12
MONTERING AF TILGANG SKRUER DEMONTERES TILGANGSKABEL MONTERES I KLEMMER MOMENTSPÆNDES MED 1,2-1,4 Nm 5 / 12
MONTERING AF AFGANGE FØRSTE KABEL PR. GRUPPE MONTERES I ØVERSTE/ BAGERSTE KLEMMERÆKKE. TILSLUT JORDLEDNING MIN. 10 mm² VED TO KABLER PR. GRUPPE MONTERES ANDET KABEL PÅ FORESTE/NEDERSTE KLEMMERÆKKE. MOMENTSPÆNDES MED 1,2-1,4 Nm 6 / 12
BATTERI NÅR DER ER SPÆNDING PÅ TAVLEN MONTERES LUS PÅ BATTERIENHED. 7 / 12
AUTOTRANSFORMER ÆNDRING FOR NIVEAU AF LYSDÆMPNING REGULERES VED AT FLYTTE LEDNING MELLEM DE FORSKELLIGE SPÆNDINGSTRIN. 8 / 12
TIMER. INDSTILLING AF LYSKILDERS OPVARMNINGSTID, FØR DÆMPNING KAN TILLADES. INDSTILLING AF TILLADTE ASYMMETRI MELLEM FASESPÆNDING PÅ DE TRE FASER. 9 / 12
AFPRØVNING OG IDRIFTSÆTNING INDEN TAVLEN IDRIFTSÆTTES SKAL DENNE EFTERSES OG AFPRØVES IHT. STÆRKSTRØMSBEKENDTGØRELSENS AFSNIT 6, KAP. 61 EFTERSYN OG AFPRØVNING FØR IDRIFTSÆTNING. VED IDRIFTSÆTNING SKAL AMPLIGHT ENHEDERNE KONTROLLERES AT DISSE VIRKER EFTER HENSIGTEN. KONTROLLER AT ALLE LYSDIODER PÅ AMPLIGHT MODULERNE LYSER/BLINKER SOM NÆVNT I INSTALLATIONS VEJLEDNINGEN. HAV SERIENUMMER PÅ CPU KLAR OG RING TIL TEKNIKGRUPPEN PÅ ET AF NEDENSTÅENDE TELEFON NUMRE FOR AT TESTE AMPLIGHT ENHEDERNE. SERIENUMMER FINDES PÅ FRONTEN AF CPU EN SAMMEN MED EN STREGKODE. TEKNIKGRUPPEN HOVED NR TLF: 76 52 22 00 DANIEL SÖNNICHSEN TLF: 25 35 02 06 10 / 12
KONTAKTOPLYSNINGER TIL LEVERANDØR: VEJBELYSNINGSSKAB: STRØM HANSEN A/S SUNDSHOLMEN 39 POSTBOKS 100 9400 NØRRESUNDBY TLF.: FAX.: 9632 6000 9632 6001 KONTAKTPERSONER: AFD. LEDER THOMAS JEPSEN LUNDH PROJEKTLEDER THOMAS MEJLHOLM VAGTTELEFON UDEN FOR DAGLIG ÅB- NINGSTID TLF.: 9632 6000 LYSSTYRING: TEKNIKGRUPPEN ALFRED JENSEN & SØN A/S LANCIAVEJ 1B 7100 VEJLE TLF.: FAX.: 7585 7545 7585 7546 KONTAKTPERSON: DATA TEKNIKER DANIEL SÖNNICHSEN 11 / 12
BILAG 1 : PRINCIP FOR FUNDERING AF VEJBELYSNINGSSKABE 12 / 12