Dato: 8/1/2012 Afslutningsskema 1. Projekttitel Generic Virtual Power Plant for optimised micro CHP Operation and Integration 2. Projektidentifikation Energinet.dk project no. 7572 3. Projektperiode (dato, år) Oktober 2007 december 2010, Forlænget til december 2011 4. Projektansvarlig virksomhed Center for Electric Technology, CET 5. Øvrige deltagere Sydenergi, EC Power, Dantherm (tidligere Danfoss) 6. Den underskriftansvarliges underskrift Dato: 8/1/2012 Navn: Chresten Træholt Underskrift:.. Dokument nr. 10833-09 sag 09/414 JBH 1/5
7. Sammenfatning af projektets formål og de opnåede resultater (Resumeet må højst fylde 2.000 karakterer. Indhøstede erfaringer og evt. betydelige afvigelser fra de oprindelige projektforventninger kommenteres) Projektet havde følgende mål: 1) at udrede koncepterne vedr. det virtuelle kraftværk (VPP), 2) at definere den nødvendige informationsudveksling for at implementere en styre-enhed for et VPP, 3) design og implementering af en VPP styre-enhed, 4) implementering, demonstration og afprøvning af et VPP i laboratoriet ved brug af bl.a. mikro-kraftvarmeværker og endelig 5) evaluering af demonstrationen. Koncepterne omkring et VPP samt det nødvendige informationsflow for hhv. et centralt styret og et decentralt styret VPP er kortlagt grundigt i en række studier og publikationer. Der har også været designet og simuleret forskellige dele af et VPP, dels centralt styret VPP, hvor en algoritme typisk har optimeret et overordnet formål for hele VPP et og dels decentralt styret VPP hvor en syntetisk pris har været udsendt til VPP et, hvor der så har været en lokal optimering af den enkelte enhed. En egentlig implementering i laboratoriet hos CET har været svær opgave. Derudover har CET laboratoriet i en længere periode (1½ år) været ude af drift p.gr.a. renovering. Enkelte dele af et VPP har været implementeret midlertidigt med én type hardware, såsom central styring af to mikro-kraftvarme enheder gennem en Siemens mikrobox og en standardiseret kommunikation (IEC61850), andre gange har en enkelt mikro-kraftvarme enhed været styret direkte på sin serielle port ved en styre-algoritme der optimerer driften lokalt i henhold til varmeforbrug og pris eller frekvensinformation. Alternativt er en proprietær centralt styrende VPP realiseret hos partner EC Power. En større afgrening af VPP arbejdet har været indenfor styring af opladningen for elektriske biler i projekt EDISON. Det er ikke lykkedes at opbygge en sammenhængende kæde med virkelige eller syntetiske prissignaler eller frekvensmålinger der via en styrealgoritme og gennem standardiseret kommunikationer udøver en overordnet styring af mange enheder. Der har således heller ikke været udført nogen større test drift eller evaluering. Dokument nr. 10833-09 sag 09/414 JBH 2/5
8. Abstract på dansk (Skal fylde ca. 600 karakterer. Der lægges vægt på resultater, der har international interesse) Gennem projektforløbet har der været en grundig kortlægning og udredning af virtuel kraftværk konceptet. Dette er sket i en række publikationer samt ved en PhD afhandling. Der har der været lavet en del simuleringer af reaktionsmønstret fra mange, dvs. 20 100 forskelligt konfigureret mikro-kraftvarmeværker. To interessante cases med markedsbaseret central styring har været studeret, dels et med en eksakt algoritme der beregner hele udfaldsrummet og finder den optimale løsning, dels en styret via et kunstigt neuralt netværk. Der har været meget arbejde med at realisere den identificeret nødvendige kommunikation vha. IEC61850 standarden. Et stort arbejde er afgrenet ud i feltet omkring elektriske biler, hvor virtuelt kraftværk har fået et fysisk udtryk i flådestyring. 9. Abstract på engelsk (Skal fylde ca. 600 karakterer. Der lægges vægt på resultater, der har international interesse) Throughout the project there has been a thorough mapping of the concepts related to virtual power plants. This was published in a number of papers as well as in a PhD thesis. A number of simulations showed the reaction patterns of many, 20 100, individually configured micro-chp s. Two interesting market based cases using centrally controlling algorithms were studied, one where the optimization is based on a full calculation of the solution space, another where the optimization is based on an artificial neural network. Further, a lot work went into mapping the necessary communication onto the IEC62850 standard. Finally, an important and large derivative is the work relating to electric vehicles where the virtual power plant has got a physical pendant in the fleet management. Dokument nr. 10833-09 sag 09/414 JBH 3/5
10. Resultatanvendelse, forretningsstrategi, offentliggørelse og formidling (Realiserede og mulige resultatanvendelser omtales, sammen med en kort beskrivelse af forretningsstrategien. Publikationer, rapporter, artikler samt indlæg om projektet ved møder og konferencer oplyses) Arbejdet omkring kortlægning og grundig udredning af konceptet virtuelt kraftværk (VPP) er publiceret og præsenteret på konferencer og workshops. Arbejdet med simulering af markedbaseret virtuelt kraftværk med anvendelse af mikro-kraftvarme enheder samt en central styring (eksakt optimeringsalgoritme og neuralt netværk) er også publiceret og præsenteret. Kortlægningen af VPP og simuleringerne og optimeringsalgoritmerne er også samlet i en PhD afhandling ved You Shi. Praktisk realisering ved implementering af IEC62850 standarden er publiceret ved bla. Peter B. Andersen, Einar B. Hauksson og Anders B Pedersen. Test med simuleret varmelager og pris-signaler er publiceret ved Preben Nyeng. I EC Powers produktportefølje indgår i dag en option for VPP styring. Projekt EDISON repræsenterer en stor og vigtig udmøntning af VPP indenfor feltet elektriske biler, hvor flådestyring ikke kun er ansporet af pooling og markedsdeltagelse, men også kan tilbyde et løsningselement ifm. potentiel overbelastning af distributionsnettet. I CET s laboratorium re-etableres 6 individuelt måle og styrbare kraftvarme testopstillinger, hvor der fremadrettet bliver mulighed for at arbejde videre med VPP. Her bliver det muligt at påtrykke veldefinerede varmelast profiler og hvor mikro-kraftvarmeværkerne kan kobles sammen med elbiler, brændselsceller og solpaneler (PV). Det er planen også at arbejde videre med VPP i EcoGrid EU regi, i PV og el-bil regi samt i sammenhæng med brændselceller, hvor man ligeledes løbende vil følge implementeringen på Bornholm. Dokument nr. 10833-09 sag 09/414 JBH 4/5
11. Finansieringsoversigt Oversigten er ikke et projektregnskab. Projektregnskabet udformes (og revisorpåtegnes for private) i overensstemmelse med gældende Regler for ForskEL, ForskNG og ForskVE projekter og indsendes separat. Lønomkostninger Overhead Apparater, udstyr, materialer Eksterne ydelser Rejser og ophold Elproduktion (kun for ForskVE-projekter) Andet Totale projektomkostninger Heraf tilskud Samlede faktiske omkostninger og tilskud Eventuelle indtægter og restanlægsværdi. Projektets reelle udgifter og tilskud Udfyldes kun for ForskVE projekter 12. Opgørelse af el leveret til elnettet i hele projektperioden År kwh eksporteret til elnettet Total Dokument nr. 10833-09 sag 09/414 JBH 5/5