Banedanmark. The Signalling Programme. Morten Søndergaard, Programme Director
|
|
|
- Lise Jette Klausen
- 9 år siden
- Visninger:
Transkript
1 Banedanmark The Signalling Programme Marts 2009 Morten Søndergaard, Programme Director
2 Agenda 1. Background 2. Technology 3. Total renewal principles 4. Roll out plans 5. Procurement and contract strategy 6. Organisation 7. Cost 2
3 Danish signalling needs to be renewed now. 60% of all signalling will exceed absolute final service-life within 15 years DK-ATC life expires in 2020 It takes years to renew all signalling assets. More systems have risk of serious breakdowns even today. 50% of todays train delays are due to signalling failures. In 2006 a total of trains were delayed. 3
4 A total renewal of the signalling system minimize total cost and provide better performance A total renewal is the best solution: Cheapest and fastest implementation Provides higher punctuality and capacity Most benefits for the passengers Benefits are achieved faster 2006: Strategic political decision of a total renewal : Detailed plans & budget for a total renewal programme January 2009: Final political decision for a fully financed total renewal programme was decided by the Danish Parliament 4
5 Two different systems Conventional network (Fjernbanen): ERTMS 2 and modern centralized signalling with fewer components S-banen: Modern metro/urban system: e.g. CBTC 5
6 ERTMS...hvad er det? ERTMS = European Railway Traffic Management System Fælles europæiske regler og standarder, der gør det muligt for tog at køre over landegrænserne uden hindringer (interoperabilitet). I dag er teknik og regler nationale, og f.eks. skal der skiftes tog og førere ved grænserne, eller togene skal dobbeltudrustes ERTMS Interoperabilitet bygger på 3 ben: ETCS = European Train Control System = ATC system GSM-R = Europæisk radiostandard EOS = European Operational Rules = Fælleseuropæiske trafikale regler for normal drift Europæisk lov ERTMS er et lovkrav. Nye ATC og radiosystemer skal være ERTMS Page 6
7 Fremtidens signalanlæg... ERTMS 1 ~ dansk ATC ERTMS Blokafsnit Længde: få 100 m til flere km Automatisk togstop = ERTMS baliser GSM-R radio ERTMS ombord signal Sporisolation el. akseltæller Sikringsanlæg Page 7
8 Fremtidens signalanlæg...ertms 2 signallering uden signaler Blokafsnit Længde: få 100 m til flere km Automatisk togstop = ERTMS baliser GSM-R Radio ERTMS ombord Signal Sporisolation el. akseltæller Sikringsanlæg Radio Blok Center Fjernstyring Page 8
9 Fremtidens signalanlæg på S-banen endnu færre komponenter i sporet CBTC = Communication Based Train Control Muliggør flydende blok og fuldautomatisk kørsel Blokafsnit Længde: få 100 m til flere km Radio ombord Sporisolation el. akseltæller Positionsbaliser Sikringsanlæg Radio Blok Center Fjernstyring Page 9
10 Many benefits for the passengers 80% reduction in signalling related train delays Higher train speed and shorter travel time on some lines A homogeneous high safety level on the whole network ERTMS - European standard free crossing of borders Better traffic information to passengers + benefits for Banedanmark Examples of RAM-requirements: Fjernbane network Normal operations maintained (not affecting normal train operation): 200 failures / year Degraded operation (some delays, few cancelled trains, failure corrected within 2 hours): 70 failures / year Emergency operation (large delays and many trains cancelled, failure corrected within 4 hours): 0,5 failure / year No operation (train operations totally or partly halted, failure cannot be corrected within 4 hours) 0,06 failure / year 10
11 The logic in total renewal Better prices Economies of scale International competition Learning curve effect Quantum leap in technology EC standard component, redundancy of central components, higher availability Few safety approvals Few interfaces Savings on operations and safety Reduction in maintenance costs Simpler and safer operational rules Fewer Traffic Management sites and reduction in staff. 11
12 Time schedules 12
13 Roll-out until 2021 Starting 2009, it will take years to carry out the total renewal Two contracts for the conventional network One framework contract for on-board equipment Contract interface at Lillebælt Roll-out phases: Early deployment Main lines Regional lines Low density lines 13
14 The S-bane One contract Technology: Suppliers well proven metro type system e.g. CBTC Early deployment line: Jægersborg - Hillerød Roll-out starting from end branches towards centre of Copenhagen Last, the central lines: Risk-minimising approach 14
15 Contract strategy Design Build Maintain contracts up to 5 years of maintenance 2 Contracts on main & regional lines (East and West) 1 Supplier 2 contracts on the S-bane including all rolling stock 1 Contract for on-board main & regional rolling stock GSM-R data included in GSM-R tender starting now Framework type contracts that allow fitting of new lines Possible option for ERTMS regional TMS Coordination by suppliers East contract West contract All supply & implementation from track to TMS Rolling stock contract 15
16 Procurement strategy and timing Performance and functional specifications Negotiated proces developing spec s with suppliers One supplier can bid for both East and West (and other contracts) Post contract partnering scheme Draft schedule S-bane Fjernbane Supplier consultation May & June + October External consultant (Tender & contract) Sept 2009 Sept 2009 Prequalification of suppliers 1.Q Q 2010 Issue of tender material 1.Q Q 2010 Negotiation with suppliers 2.Q > 3Q > Formation of supplier contracts 2.Q Q
17 Økonomiske nøgletal Alle tal i mia. kr. (2009 niveau) Fjernbanen S-banen Totaludskiftning af alle signalanlæg 15,1 3,1 Korrektions- el. risikotillæg på 30% 4,5 0,9 Totaludgift 19,6 4,0 Udgift investeringsplanen (Anlægsudgifter + korrektionstillæg i perioden) Anslået besparelse i fornyelse og vedligehold i signalanlæggets levetid (25år) 17,7 4,0 6,7 1,7
18 Contract size Major contract sizes calls for: Industrial production methods Type approval Standardized roll-out Careful testing Economy of scale The items shown reflects the configuration used in the project proposal to estimate time and cost Subject Today Future Track length in km approx: Stations Interlockings (on stations & lines) Level crossings with protection (out of 1154 in total) Train detection sections Point machines Daylight signals Yellow fleet vehicles Centralised traffic control centres 14 3 Radio Block Centre / Zone controller - 40 Trains on conventional network and S-bane Radio - GSM-R masts Signallers approx Train driversapprox
19 Safety assessement 19
20 What does it mean for Banedanmark and the employees? Reorganisation during the next 12 years with impact on: All traffic management staff in Banedanmark All signalling technicians Train drivers with the train operation companies Changes include: New operational rules New workplace systems New places of work geographically and more 20
21 Organisation Recruitment ongoing Experience ressources needed: Project Managers Disciplin managers Signalling Project Support 21
22 22
The Signalling Programme, Modern integrated signalling systems for the Railway
The Signalling Programme, Modern integrated signalling systems for the Railway 09.10.2009 Presented to TØF by Jens Holst Møller & Claus Nymark Signalprogrammet i Banedanmark Udskiftning af alle Signalanlæg
The New Line Copenhagen-Ringsted. Bentleyusers.dk 14 November 2011
The New Line Copenhagen-Ringsted Bentleyusers.dk 14 November 2011 Rail transport in Denmark The history of rail transport in Denmark began in 1847 with the opening of a railway line between Copenhagen
Velkommen. Pause med frokost
1. Introduktion og generel præsentation af Signalprogrammet, dets organisering, med særlig fokus på de igangværende aktiviteter i de kommende 2 år 2. Præsentation af GSM-R projektet, dets organisering
THE DANISH SIGNALLING PROGRAM
THE DANISH SIGNALLING PROGRAM 1 Background? Status of Early deployment section on the main Danish Rail Net + onboard + Lessons learned for the roll-out of the projects Traffic control in the Banedanmark
Gevinstrealisering i Banedanmark
Gevinstrealisering i Banedanmark Teori og praksis Marts 2016 - Årsdage for offentlige indkøb - Laura Tomassini og Nina Uldal 1 Banedanmark hvem er vi? Ejer og forvalter det danske jernbanenet Statsejet
Procuring sustainable refurbishment
SURE den 21. marts 2012 Procuring sustainable refurbishment Niels-Arne Jensen, Copenhagen City Properties (KEjd) Copenhagen Municipality KOMMUNE 1 Agenda About Copenhagen City Properties Background and
Railways and DSB traffic transition for the future
Railways and DSB traffic transition for the future DTU Transport Summit 31th of maj 2018 Lars Krogsdam, Long Term Planning A decade of transition in the Danish Railway 2 Agenda Traffical changes Timetable
Traffic Safety In Public Transport
Traffic Safety In Public Transport 13 October 2014 Arriva Denmark 2 Arriva Denmark Arriva has been part of public transport in Denmark since 1997 Arriva Denmark provides passenger transport by bus, train
Programledelse, Organisatorisk transformation og Gevinstrealisering. Praktiske erfaringer fra Signalprogrammet
Programledelse, Organisatorisk transformation og Gevinstrealisering Praktiske erfaringer fra Signalprogrammet Jacob Primault, Manager, Rambøll Management Consulting Master in economics PRINCE2, MSP, MoP
Small Autonomous Devices in civil Engineering. Uses and requirements. By Peter H. Møller Rambøll
Small Autonomous Devices in civil Engineering Uses and requirements By Peter H. Møller Rambøll BACKGROUND My Background 20+ years within evaluation of condition and renovation of concrete structures Last
Der var engang 70érne avn i 80érne industrien flytter København i 00 erne opsving København i 00érne København i 2009 Cop 15 København 2010 København 2010 Klimatilpasningsplanen København The Copenhagen
Erhvervslivets mediationsdag Siemens A/S 2015 siemens.com/answers
Siemens tilgang til tvistløsning siemens.com/answers En af Danmarks største teknologivirksomheder Etableret i Danmark i 1893 Ansatte 2014: ca. 7.200 Heraf ~1.500 ingeniører & R&D Omsætning 2014: DKK 26,1
Byg din informationsarkitektur ud fra en velafprøvet forståelsesramme The Open Group Architecture Framework (TOGAF)
Byg din informationsarkitektur ud fra en velafprøvet forståelsesramme The Open Group Framework (TOGAF) Otto Madsen Director of Enterprise Agenda TOGAF og informationsarkitektur på 30 min 1. Introduktion
PEMS RDE Workshop. AVL M.O.V.E Integrative Mobile Vehicle Evaluation
PEMS RDE Workshop AVL M.O.V.E Integrative Mobile Vehicle Evaluation NEW - M.O.V.E Mobile Testing Platform Key Requirements for Measuring Systems Robustness Shock / vibrations Change of environment Compact
Supplier development så langt kan man nå i samarbejdet mellem kunde og leverandør. Søren Jepsen 13. Juni 2013
Supplier development så langt kan man nå i samarbejdet mellem kunde og leverandør. Søren Jepsen 13. Juni 2013 Solar in short Solar is one of Northern Europe s leading technical wholesalers Listed on NASDAQ
Vores mange brugere på musskema.dk er rigtig gode til at komme med kvalificerede ønsker og behov.
På dansk/in Danish: Aarhus d. 10. januar 2013/ the 10 th of January 2013 Kære alle Chefer i MUS-regi! Vores mange brugere på musskema.dk er rigtig gode til at komme med kvalificerede ønsker og behov. Og
Lovkrav vs. udvikling af sundhedsapps
Lovkrav vs. udvikling af sundhedsapps Health apps give patients better control User Data Social media Pharma Products User behaviour Relatives www Self monitoring (app) data extract Healthcare specialists
Hvad er Asset Management
Hvad er Asset Management 1 Klaus Rosendal Head of the Water Department Grontmij Denmark M : +45 2723 6645 E: [email protected] Javier Serrano Alonso Technical Director Grontmij UK M : +44 7738
Molio specifications, development and challenges. ICIS DA 2019 Portland, Kim Streuli, Molio,
Molio specifications, development and challenges ICIS DA 2019 Portland, Kim Streuli, Molio, 2019-06-04 Introduction The current structure is challenged by different factors. These are for example : Complex
Informationsmøde for leverandører. 13. maj 2008
Informationsmøde for leverandører 13. maj 2008 Tidsplan 13.30 13.50: Velkomst v/mib+jhas 13.50 14.10: Signalprogrammet v/mors 14.10 14.35: Fornyelsesplan v/clrm 14.35 14.45: Brogruppen v/clrm 14.45 15.05:
Sesam seminar nr. 106. Sesam seminar nr. 106 - Opbygning af standard bibliotek til PLC / SCADA / MES
Sesam seminar nr. 106 Opbygning af standard software bibliotek til PLC / SCADA / MES Fokus områder: Fundament & omfang af software bibliotek Overvejelser i forbindelse med etablering af bibliotek Vedligeholdelse
Project Step 7. Behavioral modeling of a dual ported register set. 1/8/ L11 Project Step 5 Copyright Joanne DeGroat, ECE, OSU 1
Project Step 7 Behavioral modeling of a dual ported register set. Copyright 2006 - Joanne DeGroat, ECE, OSU 1 The register set Register set specifications 16 dual ported registers each with 16- bit words
Trolling Master Bornholm 2016 Nyhedsbrev nr. 3
Trolling Master Bornholm 2016 Nyhedsbrev nr. 3 English version further down Den første dag i Bornholmerlaks konkurrencen Formanden for Bornholms Trollingklub, Anders Schou Jensen (og meddomer i TMB) fik
Afgrænsning af miljøvurdering: hvordan får vi den rigtig? Chair: Lone Kørnøv MILJØVURDERINGSDAG 2012 Aalborg
Afgrænsning af miljøvurdering: hvordan får vi den rigtig? Chair: Lone Kørnøv MILJØVURDERINGSDAG 2012 Aalborg Program Intro om Systemafgrænsning og brug af LCA med fokus på kobling mellem arealindtag og
Trolling Master Bornholm 2015
Trolling Master Bornholm 2015 (English version further down) Sæsonen er ved at komme i omdrejninger. Her er det John Eriksen fra Nexø med 95 cm og en kontrolleret vægt på 11,8 kg fanget på østkysten af
Finn Gilling The Human Decision/ Gilling September Insights Danmark 2012 Hotel Scandic Aarhus City
Finn Gilling The Human Decision/ Gilling 12. 13. September Insights Danmark 2012 Hotel Scandic Aarhus City At beslutte (To decide) fra latin: de`caedere, at skære fra (To cut off) Gilling er fokuseret
Skovgaard International In Denmark and Abroad
Skovgaard International In Denmark and Abroad Skovgaard International ApS is an independent consulting company specialised in strategic planning and designing modern pig production units. Curriculum Vitae
New Hospital & New Psychiatry Bispebjerg
The Bispebjerg Construction Project EUHPN, October 2012 Hospital plan for the Capital Region A major restructuring project of the Danish hospital structure is now taking place. Each of the 5 regions develops
Kalkulation: Hvordan fungerer tal? Jan Mouritsen, professor Institut for Produktion og Erhvervsøkonomi
Kalkulation: Hvordan fungerer tal? Jan Mouritsen, professor Institut for Produktion og Erhvervsøkonomi Udbud d af kalkulationsmetoder l t Economic Value Added, Balanced Scorecard, Activity Based Costing,
Sikkerhedsvejledning
11-01-2018 2 Sikkerhedsvejledning VIGTIGT! Venligst læs disse instruktioner inden sengen samles og tages i brug Tjek at alle dele og komponenter er til stede som angivet i vejledningen Fjern alle beslagsdele
Brüel & Kjær cooperation with Turbomeca - France
Brüel & Kjær cooperation with Turbomeca - France www.bksv.com Brüel & Kjær Sound & Vibration Measurement A/S. Copyright Brüel & Kjær. All Rights Reserved. Turbomeca Turbine manufacturer - France 6,360
Sikkerhed & Revision 2013
Sikkerhed & Revision 2013 Samarbejde mellem intern revisor og ekstern revisor - og ISA 610 v/ Dorthe Tolborg Regional Chief Auditor, Codan Group og formand for IIA DK RSA REPRESENTATION WORLD WIDE 300
Managing stakeholders on major projects. - Learnings from Odense Letbane. Benthe Vestergård Communication director Odense Letbane P/S
Managing stakeholders on major projects - Learnings from Odense Letbane Benthe Vestergård Communication director Odense Letbane P/S Light Rail Day, Bergen 15 November 2016 Slide om Odense Nedenstående
Mission and Vision. ISPE Nordic PAT COP Marts Jesper Wagner, AN GROUP A/S, Mejeribakken 8, 3540 Lynge, Denmark
Mission and Vision ISPE Nordic PAT COP Marts 2007 Mission Statement To provide a professional technical group to support all levels of competence of Process Analytical Technology within the Scandinavian
Trolling Master Bornholm 2014
Trolling Master Bornholm 2014 (English version further down) Ny præmie Trolling Master Bornholm fylder 10 år næste gang. Det betyder, at vi har fundet på en ny og ganske anderledes præmie. Den fisker,
DSB s egen rejse med ny DSB App. Rubathas Thirumathyam Principal Architect Mobile
DSB s egen rejse med ny DSB App Rubathas Thirumathyam Principal Architect Mobile Marts 2018 AGENDA 1. Ny App? Ny Silo? 2. Kunden => Kunderne i centrum 1 Ny app? Ny silo? 3 Mødetitel Velkommen til Danske
Special VFR. - ved flyvning til mindre flyveplads uden tårnkontrol som ligger indenfor en kontrolzone
Special VFR - ved flyvning til mindre flyveplads uden tårnkontrol som ligger indenfor en kontrolzone SERA.5005 Visual flight rules (a) Except when operating as a special VFR flight, VFR flights shall be
Baltic Development Forum
Baltic Development Forum 1 Intelligent Water Management in Cities and Companies developing and implementing innovative solutions to help achieve this objective. Hans-Martin Friis Møller Market and Development
Totallivsomkostning som vejen frem Hvorfor leverandører af udstyr til den maritime branche bør indtænke service i deres forretningsstrategier
Totallivsomkostning som vejen frem Hvorfor leverandører af udstyr til den maritime branche bør indtænke service i deres forretningsstrategier Section for Engineering Design and Product Development Dér
Privat-, statslig- eller regional institution m.v. Andet Added Bekaempelsesudfoerende: string No Label: Bekæmpelsesudførende
Changes for Rottedatabasen Web Service The coming version of Rottedatabasen Web Service will have several changes some of them breaking for the exposed methods. These changes and the business logic behind
Studieordning del 3,
Studieordning del 3, 2014-2016 Autoteknolog, Valgfri Uddannelseselementer Academy Profession Degree in Automotive Technology Version 0.1 Revideret 19. august 2015 Side 0 af 6 Indhold Studieordningens del
Agenda Subject Time Status Annex Comments
Board Meeting - Draft Agenda Wednesday, January, 30 th From 15.00 to 20.00 19.30: Dinner Agenda 1, Annex 01 Agenda Subject Time Status Annex Comments 1. Welcome and approval of the agenda 15.00 15.10 01
Semco Maritime - Vækst under vanskelige vilkår. Offshoredag 2009 Vice President Hans-Peter Jørgensen
Semco Maritime - Vækst under vanskelige vilkår Offshoredag 2009 Vice President Hans-Peter Jørgensen Agenda Semco Maritime forretningen Vækst via internationalisering Fremtidig vækststrategi Konsekvenser
Help / Hjælp
Home page Lisa & Petur www.lisapetur.dk Help / Hjælp Help / Hjælp General The purpose of our Homepage is to allow external access to pictures and videos taken/made by the Gunnarsson family. The Association
Virk.dk. A one-stop-shop for businesses. Peter Bay Kirkegaard, [email protected] Special Advisor Danish Commerce and Companies Agency
Virk.dk A one-stop-shop for businesses Peter Bay Kirkegaard, [email protected] Special Advisor Danish Commerce and Companies Agency Agenda Background Status Future 16-10-2007 2 Virk.dk 16-10-2007 3 Vision Political
Strategic Capital ApS has requested Danionics A/S to make the following announcement prior to the annual general meeting on 23 April 2013:
Copenhagen, 23 April 2013 Announcement No. 9/2013 Danionics A/S Dr. Tværgade 9, 1. DK 1302 Copenhagen K, Denmark Tel: +45 88 91 98 70 Fax: +45 88 91 98 01 E-mail: [email protected] Website: www.danionics.dk
Generalized Probit Model in Design of Dose Finding Experiments. Yuehui Wu Valerii V. Fedorov RSU, GlaxoSmithKline, US
Generalized Probit Model in Design of Dose Finding Experiments Yuehui Wu Valerii V. Fedorov RSU, GlaxoSmithKline, US Outline Motivation Generalized probit model Utility function Locally optimal designs
Statistical information form the Danish EPC database - use for the building stock model in Denmark
Statistical information form the Danish EPC database - use for the building stock model in Denmark Kim B. Wittchen Danish Building Research Institute, SBi AALBORG UNIVERSITY Certification of buildings
Learnings from the implementation of Epic
Learnings from the implementation of Epic Appendix Picture from Region H (2016) A thesis report by: Oliver Metcalf-Rinaldo, [email protected] Stephan Mosko Jensen, [email protected] Appendix - Table of content Appendix
The City Goods Ordinance. 1. Introduction. Web: www.citygods.dk. City Gods. Certificeret. E-mail: [email protected]
1. Introduction Web: www.citygods.dk City Gods Certificeret E-mail: [email protected] 2. The City Goods ordinance - main target City Goods ordinance: Vans and lorries over 2.500kg totalweigt must be 60%
Decommissioning Development Project in Esbjerg. Foredrag hos Skibsteknisk Selskab By Peter Blach, Offshore Center Danmark
Decommissioning Development Project in Esbjerg Foredrag hos Skibsteknisk Selskab By Peter Blach, Offshore Center Danmark 1 Background More than 7000 off-shore constructions world wide More than 600 off-shore
ALLROUND 360 ONE 360 ONE SOFT SQUARY BLOCKY OWI TUBO EASY B75 EASY B100
ALLROUND 360 ONE 360 ONE SOFT SQUARY BLOCKY OWI TUBO EASY B75 EASY B100 Since the dawn of time, man has depended on the existence of light. The sun forced darkness to retreat into the shadows and made
Porteføljestyring. IDA Proces. Maj 2015 Henrik Hajslund
Porteføljestyring IDA Proces Maj 2015 Henrik Hajslund [email protected] Om Henrik Hajslund Cand.merc SOL fra CBS Har arbejdet som konsulent i >10 år. Fokus på Projekt- Portefølje- og Ressourcestyring.
Unitel EDI MT940 June 2010. Based on: SWIFT Standards - Category 9 MT940 Customer Statement Message (January 2004)
Unitel EDI MT940 June 2010 Based on: SWIFT Standards - Category 9 MT940 Customer Statement Message (January 2004) Contents 1. Introduction...3 2. General...3 3. Description of the MT940 message...3 3.1.
Elite sports stadium requirements - views from Danish municipalities
Elite sports stadium requirements - views from Danish municipalities JENS ALM Ph.d. student Malmö University [email protected] Analyst Danish Institute for Sports Studies [email protected] Background Definitions
Sport for the elderly
Sport for the elderly - Teenagers of the future Play the Game 2013 Aarhus, 29 October 2013 Ditte Toft Danish Institute for Sports Studies +45 3266 1037 [email protected] A growing group in the population
Shooting tethered med Canon EOS-D i Capture One Pro. Shooting tethered i Capture One Pro 6.4 & 7.0 på MAC OS-X 10.7.5 & 10.8
Shooting tethered med Canon EOS-D i Capture One Pro Shooting tethered i Capture One Pro 6.4 & 7.0 på MAC OS-X 10.7.5 & 10.8 For Canon EOS-D ejere der fotograferer Shooting tethered med EOS-Utility eller
Agenda. The need to embrace our complex health care system and learning to do so. Christian von Plessen Contributors to healthcare services in Denmark
Agenda The need to embrace our complex health care system and learning to do so. Christian von Plessen Contributors to healthcare services in Denmark Colitis and Crohn s association Denmark. Charlotte
From innovation to market
Nupark Accelerace From innovation to market Public money Accelerace VC Private Equity Stock market Available capital BA 2 What is Nupark Accelerace Hands-on investment and business developmentprograms
Design til digitale kommunikationsplatforme-f2013
E-travellbook Design til digitale kommunikationsplatforme-f2013 ITU 22.05.2013 Dreamers Lana Grunwald - [email protected] Iya Murash-Millo - [email protected] Hiwa Mansurbeg - [email protected] Jørgen K.
To set new standards of lifting and transportation equipment for wind turbine components. Our product groups
To set new standards of lifting and transportation equipment for wind turbine components. Our product groups Embracing the full life cycle of the wind turbine Liftra develops and supplies services to
Aktivitet Dag Start Lektioner Uge BASP0_V1006U_International Human Resource Management/Lecture/BASP0V1006U.LA_E15 onsdag 11:40 3 36 41
Aktivitet Dag Start Lektioner Uge BASP0_V1006U_International Human Resource Management/Lecture/BASP0V1006U.LA_E15 onsdag 11:40 3 36 41 BASP0_V1006U_International Human Resource Management/Lecture/BASP0V1006U.LA_E15